SOLAR Β· SOUTHEASTSolar project IC-568, Baldwin County
Solar project IC-568, Baldwin County is a 80.0 MW solar request withdrawn in the Southeast interconnection queue, in Baldwin County, Alabama, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2016 (completed)
- Withdrawn / abandonedJul 2021 (project stopped here)
- ConsentedFeb 2019 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-568
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Silverhill - Turkey Hill A 115 kV Line
- Location
- Baldwin County, Alabama
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 21 December 2016
- Agreement signed
- 5 February 2019
- Withdrawn
- July 2021
Location
Marker shows the centre of Baldwin County; the queue data does not give exact sites.
Other requests in Baldwin County
- Solar project IC-1225, Baldwin CountySolar Β· 180 MW Β· agreement signed
- Solar project IC-1224, Baldwin CountySolar Β· 80.0 MW Β· agreement signed
- Solar project 25-IC-1376, Baldwin CountySolar Β· 199 MW Β· in study
- Solar + storage project IC-999, Baldwin CountySolar + storage Β· 80.0 MW Β· suspended
- Solar + storage project IC-997, Baldwin CountySolar + storage Β· 80.0 MW Β· suspended
- Solar + storage project IC-1000, Baldwin CountySolar + storage Β· 80.0 MW Β· suspended
- Gas project IC-1253, Baldwin CountyGas Β· 684 MW Β· withdrawn
- Other project IC-860, Baldwin CountyOther Β· 400 MW Β· withdrawn
- Other project IC-861, Baldwin CountyOther Β· 400 MW Β· withdrawn
- Solar + storage project IC-879, Baldwin CountySolar + storage Β· 200 MW Β· withdrawn
- Solar + storage project IC-880, Baldwin CountySolar + storage Β· 200 MW Β· withdrawn
- Solar project IC-1178, Baldwin CountySolar Β· 160 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem