United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

SOLAR Β· SOUTHEAST

Solar project IC-568, Baldwin County

Solar project IC-568, Baldwin County is a 80.0 MW solar request withdrawn in the Southeast interconnection queue, in Baldwin County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2016 (completed)
  2. Withdrawn / abandonedJul 2021 (project stopped here)
  3. ConsentedFeb 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-568
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Silverhill - Turkey Hill A 115 kV Line
Location
Baldwin County, Alabama
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
21 December 2016
Agreement signed
5 February 2019
Withdrawn
July 2021

Location

Marker shows the centre of Baldwin County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Baldwin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem