Solar project J1173, Lenawee County

Solar project J1173, Lenawee County is a 80.0 MW solar request withdrawn in the MISO interconnection queue, in Lenawee County, Michigan, connecting to CONSUMERS ENERGY COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedJun 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1173
Grid region
MISO (Midcontinent)
Utility / transmission owner
CONSUMERS ENERGY COMPANY
Connection point (POI)
Raisin - METC Tap 138kV Line Tap
Location
Lenawee County, Michigan
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
December 2019
Withdrawn
June 2020

Location

Marker shows the centre of Lenawee County; the queue data does not give exact sites.