United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 26
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project U4-004, York County Gas |
120 MW | Withdrawn / abandoned |
| Solar project AH1-267, King And Queen County Solar |
120 MW | Withdrawn / abandoned |
| Solar project AH2-280, Hamilton County Solar |
120 MW | Withdrawn / abandoned |
| Onshore wind project N38, Hardin County Onshore wind |
120 MW | Withdrawn / abandoned |
| Solar project AH1-621, Allegany County Solar |
120 MW | Withdrawn / abandoned |
| Solar project AF1-163, Barren County Solar |
120 MW | Withdrawn / abandoned |
| Solar project AH1-605, Union County Solar |
120 MW | Withdrawn / abandoned |
| Solar + storage project AG2-517, Rock Island County Solar + storage |
120 MW | Withdrawn / abandoned |
| Solar project AG2-678, Knott County Solar |
120 MW | Withdrawn / abandoned |
| Gas project S33, Baltimore County Gas |
120 MW | Withdrawn / abandoned |
| Solar project AE1-232, Chesterfield County Solar |
120 MW | Withdrawn / abandoned |
| Solar project AE1-158, Caroline County Solar |
120 MW | Withdrawn / abandoned |
| Solar + storage project AF2-391, Hardin County Solar + storage · Naturgy Candela DevCo LLC |
120 MW | Withdrawn / abandoned |
| Solar project AG2-136, Fayette County Solar |
120 MW | Withdrawn / abandoned |
| Battery storage project AG1-248, York County Battery storage |
119 MW | Withdrawn / abandoned |
| Solar + storage project AH2-147, Logan County Solar + storage |
119 MW | Withdrawn / abandoned |
| Solar project AH1-607, Delaware County Solar |
119 MW | Withdrawn / abandoned |
| Solar project AG1-120, Dekalb County Solar · Leeward Renewable Energy Development, LLC |
119 MW | Withdrawn / abandoned |
| Solar project AG1-427, Mecklenburg County Solar · ACE Development Company II, LLC |
119 MW | Withdrawn / abandoned |
| Solar project AH1-524, Laporte County Solar |
117 MW | Withdrawn / abandoned |
| Onshore wind project AC1-187, Potter County Onshore wind |
117 MW | Withdrawn / abandoned |
| Solar project AF1-301, Louisa County Solar · Invenergy Solar Project Development LLC |
117 MW | Withdrawn / abandoned |
| Gas project AB2-009, Middlesex County Gas |
116 MW | Withdrawn / abandoned |
| Mattawoman Energy Gas |
116 MW | Withdrawn / abandoned |
| Solar project AH2-212, Madison County Solar |
115 MW | Withdrawn / abandoned |
| Solar project AH1-226, City Of Emporia County Solar · Virginia Electric and Power Company |
115 MW | Withdrawn / abandoned |
| Solar project AE2-049, Kankakee County Solar |
115 MW | Withdrawn / abandoned |
| Solar project AG2-162, Rush County Solar · Salmon Solar LLC |
115 MW | Withdrawn / abandoned |
| Other project AA2-172 Other |
115 MW | Withdrawn / abandoned |
| Solar project AC2-064, Highland County Solar |
115 MW | Withdrawn / abandoned |
| Battery storage project AG2-225, Anne Arundel County Battery storage |
115 MW | Withdrawn / abandoned |
| Solar project AG2-467, Logan County Solar · Invenergy Solar Project Development LLC |
115 MW | Withdrawn / abandoned |
| Solar project AH1-484, Henry County Solar |
115 MW | Withdrawn / abandoned |
| Solar + storage project AH1-388, Mecklenburg County Solar + storage |
115 MW | Withdrawn / abandoned |
| Gas project AH1-741, Prince William County Gas · Virginia Electric and Power Company |
115 MW | Withdrawn / abandoned |
| Gas project AB2-074, Snyder County Gas |
113 MW | Withdrawn / abandoned |
| Solar project AF2-188, White County Solar |
112 MW | Withdrawn / abandoned |
| Battery storage project AH1-477, Howard County Battery storage |
112 MW | Withdrawn / abandoned |
| Solar project AH1-014, Huntington County Solar |
112 MW | Withdrawn / abandoned |
| Mattawoman Energy Gas |
111 MW | Withdrawn / abandoned |
| Scioto Farms Solar Project Solar |
110 MW | Withdrawn / abandoned |
| Battery storage project AH1-600, Lee County Battery storage |
110 MW | Withdrawn / abandoned |
| Gas project Y3-108, Union County Gas |
110 MW | Withdrawn / abandoned |
| Solar project AF2-191, St. Joseph County Solar |
110 MW | Withdrawn / abandoned |
| Solar + storage project AD1-029, Halifax County Solar + storage |
110 MW | Withdrawn / abandoned |
| Onshore wind project S44, Mifflin County Onshore wind |
110 MW | Withdrawn / abandoned |
| Battery storage project AH1-768, Blackford County Battery storage · RWE Solar Development, LLC |
110 MW | Withdrawn / abandoned |
| Solar + storage project AF2-204, Grant County Solar + storage |
110 MW | Withdrawn / abandoned |
| Other project U1-030, Atlantic County Other |
110 MW | Withdrawn / abandoned |
| Solar project AH1-550, Licking County Solar |
110 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)