United States βΊ Grid βΊ Interconnection queues
OTHER Β· PJMOther project AA2-172
Other project AA2-172 is a 115 MW other request withdrawn in the PJM interconnection queue, connecting to ATSI.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2015 (completed)
- Withdrawn / abandonedJul 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AA2-172
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- ATSI-PSEG
- Technology
- Other: 115 MW
- Total requested
- 115 MW
- Service type
- Energy only (ERIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 April 2015
- Withdrawn
- July 2015
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem