๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2023 requests) โ€” page 23

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,063551.8 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,063 requests ยท page 23 of 42
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q529, Maricopa County
Solar + storage
199 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2027
Solar + storage project C3-129, San Juan County
Solar + storage
199 MWWithdrawn / abandoned San Juan, UTWest May 2023target 2027
Solar + storage project GI-2023-10, Arapahoe County
Solar + storage
199 MWWithdrawn / abandoned Arapahoe, COWest May 2023target 2026
Solar + storage project C3-121, Utah County
Solar + storage
199 MWWithdrawn / abandoned Utah, UTWest May 2023target 2027
Battery storage project C3-131, Salt Lake County
Battery storage
199 MWWithdrawn / abandoned Salt Lake, UTWest May 2023target 2027
Solar + storage project GI-TC-2024-24, Bent County
Solar + storage
199 MWWithdrawn / abandoned Bent, COWest May 2023target 2029
Battery storage project C3-100, Bannock County
Battery storage
199 MWWithdrawn / abandoned Bannock, IDWest May 2023target 2027
Madrone
Gas
199 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Battery storage project C3-103, Klamath County
Battery storage
199 MWWithdrawn / abandoned Klamath, ORWest May 2023target 2028
Boulevardier
Battery storage
199 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Cavalcade Storage
Battery storage
198 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
Kingman Storage
Battery storage
198 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
Solar + storage project 549, Hardin County
Solar + storage
198 MWWithdrawn / abandoned Hardin, TNSoutheast May 2023
Solar + storage project 205, Berkeley County
Solar + storage
198 MWWithdrawn / abandoned Berkeley, SCSoutheast Jun 2023target 2027
Solar + storage project GI-2023-9, Pueblo County
Solar + storage
198 MWWithdrawn / abandoned Pueblo, COWest May 2023target 2027
Solar project 563, Franklin County
Solar
198 MWWithdrawn / abandoned Franklin, ALSoutheast Jun 2023
Wind
Onshore wind
197 MWWithdrawn / abandoned Aroostook, MEISO-NE Aug 2023target 2028
Battery Storage
Battery storage
197 MWWithdrawn / abandoned Hartford, CTISO-NE Jan 2023target 2026
Battery Storage
Battery storage
196 MWWithdrawn / abandoned Hampshire, MAISO-NE Jun 2023target 2027
Solar project 582, Lawrence County
Solar
195 MWWithdrawn / abandoned Lawrence, TNSoutheast Sep 2023target 2026
Keyhole 3
Battery storage
193 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Saavi Imperial Energy Storage
Battery storage
192 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Onshore wind project GEN-2023-011, Jefferson County
Onshore wind
190 MWWithdrawn / abandoned Jefferson, NESPP Oct 2023target 2030
Solar project GEN-2023-041, Mcintosh County
Solar
190 MWWithdrawn / abandoned Mcintosh, OKSPP Oct 2023target 2030
Battery storage project C3-182, Salt Lake County
Battery storage
190 MWWithdrawn / abandoned Salt Lake, UTWest May 2023target 2029
Battery storage project PIS046, Salt Lake County
Battery storage
190 MWWithdrawn / abandoned Salt Lake, UTWest Dec 2023target 2027
Solar + storage project 201, Kershaw County
Solar + storage
190 MWWithdrawn / abandoned Kershaw, SCSoutheast Jun 2023target 2027
Battery Storage
Battery storage
190 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2023target 2027
Battery storage project J2766, Howard County
Battery storage
190 MWWithdrawn / abandoned Howard, INMISO Aug 2023target 2025
Noor Solar
Solar ยท Industrial Kilo Project LLC
188 MWWithdrawn / abandoned Liberty, TXERCOT Oct 2023target 2028
Delta Lake Irrigation District 1 Solar
Solar ยท Mestenas Floating Solar LLC
187 MWWithdrawn / abandoned Hidalgo, TXERCOT May 2023target 2027
Solar + storage project GEN-2022-173, Red Willow County
Solar + storage
184 MWWithdrawn / abandoned Red Willow, NESPP Feb 2023target 2027
NY New Scotland 99 New Scotland South Rd Storage
Battery storage ยท Bluewave Origination LLC
181 MWWithdrawn / abandoned Albany, NYNYISO Aug 2023
Meadow Ridge 2
Solar + storage
181 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Sugarloaf BESS
Battery storage ยท Empire Reserve Energy, LLC
180 MWWithdrawn / abandoned Orange, NYNYISO Jun 2023
Battery Storage
Battery storage
180 MWWithdrawn / abandoned Windsor, VTISO-NE Apr 2023target 2027
Replacing 180MW with BESS of the existing 280 MW Steam; LANSING 4
Other
180 MWWithdrawn / abandoned Allamakee, IAMISO Sep 2023target 2026
Elevate Arthur Kill II, LLC
Battery storage ยท Elevate Arthur Kill, LLC
180 MWWithdrawn / abandoned Richmond, NYNYISO Apr 2023
Solar + storage project Q547, Pinal County
Solar + storage
180 MWWithdrawn / abandoned Pinal, AZWest Sep 2023target 2027
Solar + storage project CS23-04, Adams County
Solar + storage
180 MWWithdrawn / abandoned Adams, WAWest Apr 2023target 2026
Solar project GEN-2023-145, Muskogee County
Solar
180 MWWithdrawn / abandoned Muskogee, OKSPP Oct 2023target 2029
Battery storage project 546, Anderson County
Battery storage
180 MWWithdrawn / abandoned Anderson, TNSoutheast Apr 2023target 2026
Littlejohns Energy Center
Solar + storage
179 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Brackens Solar
Solar ยท Brackens Solar
177 MWWithdrawn / abandoned Freestone, TXERCOT May 2023target 2027
Solar + storage project C3-119, Natrona County
Solar + storage
176 MWWithdrawn / abandoned Natrona, WYWest May 2023target 2026
Battery Storage
Battery storage
176 MWWithdrawn / abandoned Bristol, MAISO-NE Jul 2023target 2024
Battery Storage
Battery storage
175 MWWithdrawn / abandoned New London, CTISO-NE Jun 2023target 2027
Battery storage project C3-168, Owyhee County
Battery storage
175 MWWithdrawn / abandoned Owyhee, IDWest May 2023target 2026
Solar + storage project 190, Williamsburg County
Solar + storage
175 MWWithdrawn / abandoned Williamsburg, SCSoutheast Jun 2023target 2027
Solar project 571, Hickman County
Solar
175 MWWithdrawn / abandoned Hickman, KYSoutheast Jun 2023target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)