United States βΊ Grid βΊ Interconnection queues βΊ Tennessee
BATTERY STORAGE Β· SOUTHEASTBattery storage project 546, Anderson County
Battery storage project 546, Anderson County is a 180 MW battery storage request withdrawn in the Southeast interconnection queue, in Anderson County, Tennessee, connecting to Tennessee Valley Authority.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 546
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Location
- Anderson County, Tennessee
- Technology
- Battery: 180 MW
- Total requested
- 180 MW
- Queue status
- Withdrawn
- Entered queue
- 17 April 2023
- Proposed online date
- June 2026
Location
Marker shows the centre of Anderson County; the queue data does not give exact sites.
Power plants in Tennessee Β· Transmission lines in Tennessee
Other requests in Anderson County
- Other project 198, Anderson CountyOther Β· 45.0 MW Β· built
- Other project 18, Anderson CountyOther Β· 40.0 MW Β· built
- Other project 18Other Β· 40.0 MW Β· built
- Nuclear project 240, Anderson CountyNuclear Β· 720 MW Β· withdrawn
- Gas project 228, Anderson CountyGas Β· 640 MW Β· withdrawn
- Other project 156, Anderson CountyOther Β· 17.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem