United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2016 requests) โ€” page 23

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,194150.9 GW
Active in queue25.8 GW162 requests
Agreement signed18.1 GW106 requests
Withdrawn1,194150.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,194 requests ยท page 23 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 842, Linn County
Solar
3.0 MWWithdrawn / abandoned Linn, ORWest Dec 2016target 2019
Solar project 267, Hill County
Solar
3.0 MWWithdrawn / abandoned Hill, MTWest Mar 2016target 2017
Solar project 251, Phillips County
Solar
3.0 MWWithdrawn / abandoned Phillips, MTWest Feb 2016target 2016
Solar project 272, Judith Basin County
Solar
3.0 MWWithdrawn / abandoned Judith Basin, MTWest Apr 2016target 2016
Solar project 274, Cascade County
Solar
3.0 MWWithdrawn / abandoned Cascade, MTWest Apr 2016target 2017
Solar project 282, Golden Valley County
Solar
3.0 MWWithdrawn / abandoned Golden Valley, MTWest May 2016target 2017
Solar project 263, Teton County
Solar
3.0 MWWithdrawn / abandoned Teton, MTWest Mar 2016target 2017
Solar project 265, Cascade County
Solar
3.0 MWWithdrawn / abandoned Cascade, MTWest Mar 2016target 2017
Solar project 245, Carbon County
Solar
3.0 MWWithdrawn / abandoned Carbon, MTWest Feb 2016target 2016
Solar project 258, Phillips County
Solar
3.0 MWWithdrawn / abandoned Phillips, MTWest Feb 2016target 2016
Solar project 728, Umatilla County
Solar
3.0 MWWithdrawn / abandoned Umatilla, ORWest Feb 2016target 2017
Solar project 304, Judith Basin County
Solar
3.0 MWWithdrawn / abandoned Judith Basin, MTWest Nov 2016target 2020
Solar project 243, Chouteau County
Solar
3.0 MWWithdrawn / abandoned Chouteau, MTWest Feb 2016target 2016
Solar project 276, Hill County
Solar
3.0 MWWithdrawn / abandoned Hill, MTWest May 2016target 2017
Solar project AC1-228, Dorchester County
Solar
3.0 MWWithdrawn / abandoned Dorchester, MDPJM Oct 2016target 2018
Solar project AB2-035, Pitt County
Solar
3.0 MWWithdrawn / abandoned Pitt, NCPJM Feb 2016target 2016
Solar project 273, Fergus County
Solar
3.0 MWWithdrawn / abandoned Fergus, MTWest Apr 2016target 2017
Solar project 268, Hill County
Solar
3.0 MWWithdrawn / abandoned Hill, MTWest Mar 2016target 2017
Solar project 283, Musselshell County
Solar
3.0 MWWithdrawn / abandoned Musselshell, MTWest May 2016target 2017
Solar project 247, Pondera County
Solar
3.0 MWWithdrawn / abandoned Pondera, MTWest Feb 2016target 2016
Onshore wind project 261, Wheatland County
Onshore wind
3.0 MWWithdrawn / abandoned Wheatland, MTWest Mar 2016target 2017
Solar project 308, Madison County
Solar
3.0 MWWithdrawn / abandoned Madison, MTWest Nov 2016target 2020
Solar project 818, Lake County
Solar
3.0 MWWithdrawn / abandoned Lake, ORWest Nov 2016target 2018
Solar project 241, Liberty County
Solar
3.0 MWWithdrawn / abandoned Liberty, MTWest Feb 2016target 2016
Solar project AC2-005, Dorchester County
Solar
3.0 MWWithdrawn / abandoned Dorchester, MDPJM Nov 2016target 2018
Solar project 296, Madison County
Solar
3.0 MWWithdrawn / abandoned Madison, MTWest Jul 2016target 2017
Gas project 841, Davis County
Gas
2.8 MWWithdrawn / abandoned Davis, UTWest Dec 2016target 2018
Solar project 253, Wheatland County
Solar
2.5 MWWithdrawn / abandoned Wheatland, MTWest Feb 2016target 2016
Meadow Road Solar
Solar
2.5 MWWithdrawn / abandoned Middlesex, NJPJM Mar 2016target 2018
Solar project AC1-138, Boone County
Solar
2.5 MWWithdrawn / abandoned Boone, KYPJM Oct 2016target 2017
Hydro project 843, Umatilla County
Hydro
2.2 MWWithdrawn / abandoned Umatilla, ORWest Dec 2016target 2020
Hydro project 844, Umatilla County
Hydro
2.2 MWWithdrawn / abandoned Umatilla, ORWest Dec 2016target 2020
Solar project 295, Madison County
Solar
2.2 MWWithdrawn / abandoned Madison, MTWest Jul 2016target 2017
Solar project AB2-118, Cecil County
Solar
2.0 MWWithdrawn / abandoned Cecil, MDPJM Apr 2016target 2017
Solar project 758, Klamath County
Solar
2.0 MWWithdrawn / abandoned Klamath, ORWest Jun 2016target 2018
Solar project AC1-136, Johnson County
Solar
2.0 MWWithdrawn / abandoned Johnson, KYPJM Oct 2016target 2017
Solar project 5037, Columbus County
Solar
2.0 MWWithdrawn / abandoned Columbus, NCSoutheast Apr 2016
Solar project AB2-117, Cecil County
Solar
2.0 MWWithdrawn / abandoned Cecil, MDPJM Apr 2016target 2017
Solar project AB2-113, Cecil County
Solar
2.0 MWWithdrawn / abandoned Cecil, MDPJM Apr 2016target 2017
Solar project AB2-116, Cecil County
Solar
2.0 MWWithdrawn / abandoned Cecil, MDPJM Apr 2016target 2017
Solar project AB2-115, Cecil County
Solar
2.0 MWWithdrawn / abandoned Cecil, MDPJM Apr 2016target 2017
Hydro project 834, Klamath County
Hydro
2.0 MWWithdrawn / abandoned Klamath, ORWest Dec 2016target 2017
Solar project 727, Klamath County
Solar
2.0 MWWithdrawn / abandoned Klamath, ORWest Feb 2016target 2018
Solar project AC1-032, Will County
Solar
2.0 MWWithdrawn / abandoned Will, ILPJM Aug 2016target 2017
Solar project AB2-114, Cecil County
Solar
2.0 MWWithdrawn / abandoned Cecil, MDPJM Apr 2016target 2017
Hydro project 750, Umatilla County
Hydro
2.0 MWWithdrawn / abandoned Umatilla, ORWest May 2016target 2020
Solar project AC1-031, Carroll County
Solar
2.0 MWWithdrawn / abandoned Carroll, MDPJM Aug 2016target 2017
Solar project 264, Chouteau County
Solar
2.0 MWWithdrawn / abandoned Chouteau, MTWest Mar 2016target 2017
Winzinger Egg Harbor Solar Project
Solar
1.9 MWWithdrawn / abandoned Atlantic, NJPJM Apr 2016target 2021
Solar project AC1-137, Boone County
Solar
1.9 MWWithdrawn / abandoned Boone, KYPJM Oct 2016target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)