SOLAR Β· WEST

Solar project 264, Chouteau County

Solar project 264, Chouteau County is a 2.0 MW solar request withdrawn in the West interconnection queue, in Chouteau County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
264
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Geraldine Substation, Geraldine, MT
Location
Chouteau County, Montana
Technology
Solar: 2.0 MW
Total requested
2.0 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
21 March 2016
Proposed online date
March 2017

Location

Marker shows the centre of Chouteau County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Chouteau County