United States › Grid › Interconnection queues › Montana
BATTERY STORAGE · WESTBattery storage project 443, Chouteau County
Battery storage project 443, Chouteau County is a 2.4 MW battery storage request built and operating in the West interconnection queue, in Chouteau County, Montana, connecting to NorthWestern Energy.
Request details
- Queue ID
- 443
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- Geraldine, MT
- Location
- Chouteau County, Montana
- Technology
- Battery: 2.4 MW
- Total requested
- 2.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study 8/29/2023 System Impact Study 11/21/2023 Facilities Study 1/25/2024
- Queue status
- Operational
- Entered queue
- 6 July 2023
- Proposed online date
- August 2024
- Came online
- August 2024
Location
Marker shows the centre of Chouteau County; the queue data does not give exact sites.
Other requests in Chouteau County
- Onshore wind project 287, Chouteau CountyOnshore wind · 20.0 MW · withdrawn
- Onshore wind project 286, Chouteau CountyOnshore wind · 18.0 MW · withdrawn
- Solar project 255, Chouteau CountySolar · 3.0 MW · withdrawn
- Solar project 277, Chouteau CountySolar · 3.0 MW · withdrawn
- Solar project 250, Chouteau CountySolar · 3.0 MW · withdrawn
- Solar project 257, Chouteau CountySolar · 3.0 MW · withdrawn
- Solar project 329, Chouteau CountySolar · 3.0 MW · withdrawn
- Solar project 243, Chouteau CountySolar · 3.0 MW · withdrawn
- Solar project 264, Chouteau CountySolar · 2.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem