United States βΊ Grid βΊ Interconnection queues βΊ Montana
SOLAR Β· WESTSolar project 250, Chouteau County
Solar project 250, Chouteau County is a 3.0 MW solar request withdrawn in the West interconnection queue, in Chouteau County, Montana, connecting to NorthWestern Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2016 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 250
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- Loma Substation, Loma, MT
- Location
- Chouteau County, Montana
- Technology
- Solar: 3.0 MW
- Total requested
- 3.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- System Impact Study System Impact-Re-Study
- Queue status
- Withdrawn
- Entered queue
- 29 February 2016
- Proposed online date
- November 2016
Location
Marker shows the centre of Chouteau County; the queue data does not give exact sites.
Other requests in Chouteau County
- Battery storage project 443, Chouteau CountyBattery storage Β· 2.4 MW Β· built
- Onshore wind project 287, Chouteau CountyOnshore wind Β· 20.0 MW Β· withdrawn
- Onshore wind project 286, Chouteau CountyOnshore wind Β· 18.0 MW Β· withdrawn
- Solar project 255, Chouteau CountySolar Β· 3.0 MW Β· withdrawn
- Solar project 277, Chouteau CountySolar Β· 3.0 MW Β· withdrawn
- Solar project 257, Chouteau CountySolar Β· 3.0 MW Β· withdrawn
- Solar project 329, Chouteau CountySolar Β· 3.0 MW Β· withdrawn
- Solar project 243, Chouteau CountySolar Β· 3.0 MW Β· withdrawn
- Solar project 264, Chouteau CountySolar Β· 2.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem