πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

SOLAR Β· WEST

Solar project 251, Phillips County

Solar project 251, Phillips County is a 3.0 MW solar request withdrawn in the West interconnection queue, in Phillips County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
251
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Malta City Substation, Malta, MT
Location
Phillips County, Montana
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
29 February 2016
Proposed online date
November 2016

Location

Marker shows the centre of Phillips County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Phillips County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem