SOLAR Β· WEST

Solar project 253, Wheatland County

Solar project 253, Wheatland County is a 2.5 MW solar request withdrawn in the West interconnection queue, in Wheatland County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
253
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Harlowton Substation, Harlowton, MT
Location
Wheatland County, Montana
Technology
Solar: 2.5 MW
Total requested
2.5 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
29 February 2016
Proposed online date
November 2016

Location

Marker shows the centre of Wheatland County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Wheatland County