SOLAR Β· WESTSolar project 241, Liberty County
Solar project 241, Liberty County is a 3.0 MW solar request withdrawn in the West interconnection queue, in Liberty County, Montana, connecting to NorthWestern Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2016 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 241
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- Chester Substation, Chester, MT
- Location
- Liberty County, Montana
- Technology
- Solar: 3.0 MW
- Total requested
- 3.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- System Impact Study Facilities Study
- Queue status
- Withdrawn
- Entered queue
- 3 February 2016
- Proposed online date
- November 2016
Location
Marker shows the centre of Liberty County; the queue data does not give exact sites.
Other requests in Liberty County
- Hydro project GI-0122, Liberty CountyHydro Β· 8.0 MW Β· built
- Other project hist_q68, Liberty CountyOther Β· 7.5 MW Β· built
- Onshore wind project GI-0814, Liberty CountyOnshore wind Β· 90.0 MW Β· withdrawn
- Onshore wind project 47, Liberty CountyOnshore wind Β· 20.0 MW Β· withdrawn
- Onshore wind project 161, Liberty CountyOnshore wind Β· 10.0 MW Β· withdrawn
- Solar project 249, Liberty CountySolar Β· 3.0 MW Β· withdrawn
- Solar project 278, Liberty CountySolar Β· 3.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem