πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

SOLAR Β· WEST

Solar project 263, Teton County

Solar project 263, Teton County is a 3.0 MW solar request withdrawn in the West interconnection queue, in Teton County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
263
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Choteau Substation
Location
Teton County, Montana
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
21 March 2016
Proposed online date
March 2017

Location

Marker shows the centre of Teton County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Teton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem