United States βΊ Grid βΊ Interconnection queues βΊ Utah
GAS Β· WESTGas project 841, Davis County
Gas project 841, Davis County is a 2.8 MW gas request withdrawn in the West interconnection queue, in Davis County, Utah, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2016 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 841
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Circuit CUD11 out of Cudahy substation
- Location
- Davis County, Utah
- Technology
- Gas: 2.8 MW
- Total requested
- 2.8 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN BY CUSTOMER
- Queue status
- Withdrawn
- Entered queue
- 20 December 2016
- Proposed online date
- April 2018
Location
Marker shows the centre of Davis County; the queue data does not give exact sites.
Other requests in Davis County
- Solar project 630, Davis CountySolar Β· 1.0 MW Β· built
- Battery storage project C2-69, Davis CountyBattery storage Β· 150 MW Β· withdrawn
- Other project 655, Davis CountyOther Β· 7.1 MW Β· withdrawn
- Solar project 252, Davis CountySolar Β· 0.2 MW Β· withdrawn
- Hydro project 908, Davis CountyHydro Β· 0.2 MW Β· withdrawn
- Battery storage project 965, Davis CountyBattery storage Β· 0.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem