BATTERY STORAGE Β· WEST

Battery storage project 965, Davis County

Battery storage project 965, Davis County is a 0.0 MW battery storage request withdrawn in the West interconnection queue, in Davis County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
965
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Circuit FAR13 out of Farmington substation
Location
Davis County, Utah
Technology
Battery: 0.0 MW
Total requested
0.0 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
19 October 2017
Proposed online date
October 2017

Location

Marker shows the centre of Davis County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Davis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem