United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2020 requests) โ€” page 21

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,752246.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,752 requests ยท page 21 of 36
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AF2-076, City Of Suffolk County
Solar
50.0 MWWithdrawn / abandoned City Of Suffolk, VAPJM Jan 2020target 2023
Battery storage project J1505, Washington Parish County
Battery storage
50.0 MWWithdrawn / abandoned Washington Parish, LAMISO Jun 2020target 2023
Solar project AF2-218, Darke County
Solar
50.0 MWWithdrawn / abandoned Darke, OHPJM Mar 2020target 2024
Glade Run Solar Energy Center
Solar
50.0 MWWithdrawn / abandoned Preston, WVPJM Sep 2020target 2028
Solar + storage project GEN-2020-033, Sarpy County
Solar + storage
50.0 MWWithdrawn / abandoned Sarpy, NESPP Apr 2020target 2023
Battery storage project J1496, Olmsted County
Battery storage
50.0 MWWithdrawn / abandoned Olmsted, MNMISO Jun 2020target 2023
Battery storage project J1739, Waushara County
Battery storage
50.0 MWWithdrawn / abandoned Waushara, WIMISO Jun 2020target 2023
Battery storage project J1660, Genesee County
Battery storage
50.0 MWWithdrawn / abandoned Genesee, MIMISO Jun 2020target 2023
Solar project AG1-417, Whitley County
Solar
50.0 MWWithdrawn / abandoned Whitley, INPJM Sep 2020target 2023
Onshore wind project J1774, Warren County
Onshore wind
50.0 MWWithdrawn / abandoned Warren, INMISO Jun 2020target 2023
Solar project AG1-179, Sussex County
Solar ยท Merchant Solar, LLC
50.0 MWWithdrawn / abandoned Sussex, VAPJM Sep 2020target 2023
Battery storage project AG1-464, Kent County
Battery storage
50.0 MWWithdrawn / abandoned Kent, DEPJM Sep 2020target 2023
Wading River Energy Center
Battery storage ยท Clean Energy Generation, LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Nov 2020
Solar project AG1-352, Boyle County
Solar
50.0 MWWithdrawn / abandoned Boyle, KYPJM Sep 2020target 2023
Solar + storage project AG1-325, Augusta County
Solar + storage
50.0 MWWithdrawn / abandoned Augusta, VAPJM Sep 2020target 2023
Solar project AF2-331, Montour County
Solar
50.0 MWWithdrawn / abandoned Montour, PAPJM Mar 2020target 2023
Battery storage project AG1-422, Augusta County
Battery storage ยท Leeward Renewable Energy Development, LLC
50.0 MWWithdrawn / abandoned Augusta, VAPJM Sep 2020target 2023
Solar project AG1-091, Pulaski County
Solar
50.0 MWWithdrawn / abandoned Pulaski, VAPJM Jul 2020target 2023
Battery storage project AF2-072, Monmouth County
Battery storage
50.0 MWWithdrawn / abandoned Monmouth, NJPJM Jan 2020target 2023
Ladysmith Battery Storage
Battery storage ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
50.0 MWWithdrawn / abandoned Caroline, VAPJM Sep 2020target 2023
Battery storage project AG1-470, Washington County
Battery storage
50.0 MWWithdrawn / abandoned Washington, MDPJM Oct 2020target 2024
Solar + storage project AG1-518, City Of Suffolk County
Solar + storage
50.0 MWWithdrawn / abandoned City Of Suffolk, VAPJM Sep 2020target 2023
Battery storage project J1498, Murray County
Battery storage
50.0 MWWithdrawn / abandoned Murray, MNMISO Jun 2020target 2023
Battery Storage
Battery storage
50.0 MWWithdrawn / abandoned New Haven, CTISO-NE Aug 2020target 2022
Solar project AF2-056, Schuylkill County
Solar ยท Locust Ridge Solar LLC
50.0 MWWithdrawn / abandoned Schuylkill, PAPJM Jan 2020target 2023
Battery storage project AG1-072, Queen Anne's County
Battery storage
50.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Jul 2020target 2023
Solar project AF2-051, Crawford County
Solar
50.0 MWWithdrawn / abandoned Crawford, PAPJM Jan 2020target 2023
Hart Solar
Solar ยท Thoroughbred Solar, LLC
50.0 MWWithdrawn / abandoned Hart, KYPJM Mar 2020target 2022
Boca Chica Solar
Solar ยท Tenaska Solar XVIII, LLC
50.0 MWWithdrawn / abandoned Cameron, TXERCOT Jan 2020target 2023
Battery storage project 455, Clay County
Battery storage
50.0 MWWithdrawn / abandoned Clay, MSSoutheast Aug 2020
Solar project AG1-183, King And Queen County
Solar
50.0 MWWithdrawn / abandoned King And Queen, VAPJM Sep 2020target 2023
Battery storage project AG1-463, Mercer County
Battery storage
50.0 MWWithdrawn / abandoned Mercer, PAPJM Sep 2020target 2024
Mainspring Grid
Battery storage ยท Mainspring Grid, LLC
50.0 MWWithdrawn / abandoned Amherst, VAPJM Sep 2020target 2023
Battery storage project J1499, Union County
Battery storage
50.0 MWWithdrawn / abandoned Union, ARMISO Jun 2020target 2023
Solar project AG2-067, Brunswick County
Solar
50.0 MWWithdrawn / abandoned Brunswick, VAPJM Dec 2020target 2025
Battery storage project J1494, Chisago County
Battery storage
50.0 MWWithdrawn / abandoned Chisago, MNMISO Jun 2020target 2023
Battery storage project J1523, Leflore County
Battery storage
50.0 MWWithdrawn / abandoned Leflore, MSMISO Jun 2020target 2023
Battery storage project AF2-266, Charlotte County
Battery storage
50.0 MWWithdrawn / abandoned Charlotte, VAPJM Mar 2020target 2022
Solar project AF2-439, Adams County
Solar
50.0 MWWithdrawn / abandoned Adams, PAPJM Mar 2020target 2023
Battery storage project J1493, Hubbard County
Battery storage
50.0 MWWithdrawn / abandoned Hubbard, MNMISO Jun 2020target 2023
Battery storage project J1495, Goodhue County
Battery storage
50.0 MWWithdrawn / abandoned Goodhue, MNMISO Jun 2020target 2023
Battery storage project J1693, Chippewa County
Battery storage
50.0 MWWithdrawn / abandoned Chippewa, MNMISO Jun 2020target 2023
Battery storage project J1507, Washington Parish County
Battery storage
50.0 MWWithdrawn / abandoned Washington Parish, LAMISO Jun 2020target 2023
Battery storage project J1665, St. Clair County
Battery storage
50.0 MWWithdrawn / abandoned St. Clair, MIMISO Jun 2020target 2023
Mt Vernon Solar
Solar + storage
50.0 MWWithdrawn / abandoned Warren, NJPJM Sep 2020target 2029
Prairie Refuge Solar
Solar
50.0 MWWithdrawn / abandoned Cass, MIPJM Mar 2020target 2028
Solar project AG1-234, Greenbrier County
Solar
50.0 MWWithdrawn / abandoned Greenbrier, WVPJM Sep 2020target 2024
Solar project AF2-362, Lancaster County
Solar
50.0 MWWithdrawn / abandoned Lancaster, VAPJM Mar 2020target 2023
Battery storage project J1601, Marion County
Battery storage
50.0 MWWithdrawn / abandoned Marion, INMISO Jun 2020target 2023
Solar + storage project AG1-547, Pittsylvania County
Solar + storage ยท Curie Solar, LLC
50.0 MWWithdrawn / abandoned Pittsylvania, VAPJM Sep 2020target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)