United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

BATTERY STORAGE Β· MISO

Battery storage project J1499, Union County

Battery storage project J1499, Union County is a 50.0 MW battery storage request withdrawn in the MISO interconnection queue, in Union County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedFeb 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1499
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
El Dorado East - Sterlington 115 kV
Location
Union County, Arkansas
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
8 June 2020
Proposed online date
September 2023
Withdrawn
February 2023

Location

Marker shows the centre of Union County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Union County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem