United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2016 requests) โ€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,194150.9 GW
Active in queue25.8 GW162 requests
Agreement signed18.1 GW106 requests
Withdrawn1,194150.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,194 requests ยท page 2 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Q55, Kern County
Solar
500 MWWithdrawn / abandoned Kern, CAWest Aug 2016target 2021
Solar project GI-2016-9, Alamosa County
Solar
480 MWWithdrawn / abandoned Alamosa, COWest Apr 2016target 2023
Staked Plains Wind 2
Onshore wind ยท Lincoln Clean
454 MWWithdrawn / abandoned ERCOT Mar 2016target 2019
LA450S
Solar
450 MWWithdrawn / abandoned Luna, NMWest Sep 2016target 2019
Mad River Wind
Onshore wind ยท Atlantic Wind, LLC
450 MWWithdrawn / abandoned Jefferson, NYNYISO Sep 2016
Solar project Company 148, Clark County
Solar
440 MWWithdrawn / abandoned Clark, NVWest Mar 2016target 2018
Onshore wind project GEN-2016-159, Stanton County
Onshore wind
428 MWWithdrawn / abandoned Stanton, NESPP Nov 2016target 2020
Creekside
Battery storage
418 MWWithdrawn / abandoned Santa Clara, CACAISO May 2016target 2020
All American Solar
Solar
415 MWWithdrawn / abandoned Kern, CACAISO May 2016target 2020
Grapevine 1
Battery storage
406 MWWithdrawn / abandoned Kern, CACAISO May 2016target 2020
Linwood Solar Farm
Solar + storage
405 MWWithdrawn / abandoned Kern, CACAISO May 2016target 2019
Onshore wind project J578, Audubon County
Onshore wind
400 MWWithdrawn / abandoned Audubon, IAMISO May 2016target 2018
Signal Peak
Solar
400 MWWithdrawn / abandoned Yuma, AZCAISO May 2016target 2021
Onshore wind project GEN-2016-120, Crosby County
Onshore wind
400 MWWithdrawn / abandoned Crosby, TXSPP Nov 2016target 2020
Duck Creek W
Onshore wind ยท Terra-Gen
400 MWWithdrawn / abandoned ERCOT Nov 2016target 2019
Solar project Q247, Yuma County
Solar
400 MWWithdrawn / abandoned Yuma, AZWest Sep 2016target 2021
Onshore wind project GEN-2016-044, Logan County
Onshore wind
400 MWWithdrawn / abandoned Logan, NDSPP Mar 20162018
Sanco Solar
Solar ยท 8minutenergy
400 MWWithdrawn / abandoned ERCOT Aug 2016target 2019
Lake Spring Solar
Solar ยท 8minutenergy
400 MWWithdrawn / abandoned ERCOT Jun 2016target 2020
Onshore wind project J671, Martin County
Onshore wind
400 MWWithdrawn / abandoned Martin, MNMISO Jul 2016target 2019
Onshore wind project J682, Schuyler County
Onshore wind
400 MWWithdrawn / abandoned Schuyler, MOMISO Jul 2016target 2019
Solar project 298, Haywood County
Solar
400 MWWithdrawn / abandoned Haywood, TNSoutheast Jun 2016
Onshore wind project GEN-2016-104, Sumner County
Onshore wind
400 MWWithdrawn / abandoned Sumner, KSSPP Nov 2016target 2019
Zapata II W
Onshore wind ยท Nextera
400 MWWithdrawn / abandoned Zapata, TXERCOT Jan 2016target 2019
Lacy Creek W
Onshore wind ยท Terra-Gen
400 MWWithdrawn / abandoned ERCOT Nov 2016target 2019
Santa Rita Solar
Solar ยท Invenergy
400 MWWithdrawn / abandoned Crockett, TXERCOT Nov 2016target 2022
Solar project G0549, Lake County
Solar
400 MWWithdrawn / abandoned Lake, ORWest Jul 2016target 2022
Onshore wind project J744, Lincoln County
Onshore wind
400 MWWithdrawn / abandoned Lincoln, SDMISO Nov 2016target 2020
Onshore wind project J627, Meeker County
Onshore wind
400 MWWithdrawn / abandoned Meeker, MNMISO May 2016target 2019
Onshore wind project J626, Meeker County
Onshore wind
400 MWWithdrawn / abandoned Meeker, MNMISO May 2016target 2019
Onshore wind project J773, Codington County
Onshore wind
400 MWWithdrawn / abandoned Codington, SDMISO Nov 2016target 2019
Gas project G0531, Morrow County
Gas
400 MWWithdrawn / abandoned Morrow, ORWest Feb 2016target 2021
Onshore wind project GEN-2016-106, Keith County
Onshore wind
400 MWWithdrawn / abandoned Keith, NESPP Nov 20162020
Onshore wind project GEN-2016-076, Roosevelt County
Onshore wind
396 MWWithdrawn / abandoned Roosevelt, NMSPP Jun 2016target 2018
Gas project AB2-141, Marshall County
Gas
394 MWWithdrawn / abandoned Marshall, WVPJM Apr 2016target 2019
Astoria Generating Unit 4
Gas ยท Astoria Generating Company LP
385 MWWithdrawn / abandoned New York, NYNYISO Jul 2016
Astoria Generating Unit 4
Gas ยท Astoria Generating Company LP
385 MWWithdrawn / abandoned New York, NYNYISO Sep 2016
Gas project AB2-146, Henry County
Gas
382 MWWithdrawn / abandoned Henry, VAPJM Apr 2016target 2021
Southland
Solar
380 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2023
Wind
Onshore wind
376 MWWithdrawn / abandoned Aroostook, MEISO-NE Dec 2016target 2019
Solar project 772, Iron County
Solar
375 MWWithdrawn / abandoned Iron, UTWest Jul 2016target 2018
Gas project AC1-159, City Of Chesapeake County
Gas
369 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Oct 2016target 2021
Onshore wind project G0543, Umatilla County
Onshore wind
350 MWWithdrawn / abandoned Umatilla, ORWest Jun 2016target 2019
Garden Prairie Energy Facility
Gas
350 MWWithdrawn / abandoned Boone, ILPJM Apr 2016target 2024
Mission Rock
Gas
326 MWWithdrawn / abandoned Ventura, CACAISO May 2016target 2020
Onshore wind project GEN-2016-116, Dixon County
Onshore wind
320 MWWithdrawn / abandoned Dixon, NESPP Nov 2016target 2019
Pelican Island
Solar
311 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2020
Onshore wind project GEN-2016-049, Rush County
Onshore wind
310 MWWithdrawn / abandoned Rush, KSSPP Mar 2016target 2018
Century Solar
Solar
310 MWWithdrawn / abandoned Maricopa, AZCAISO May 2016target 2021
Sand Solar
Solar
309 MWWithdrawn / abandoned San Bernardino, CACAISO May 2016target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)