United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· ERCOT

Lake Spring Solar

Lake Spring Solar is a 400 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0002
Grid region
ERCOT (Texas)
Developer
8minutenergy
Connection point (POI)
79501 Ogallala 345kV
Technology
Solar: 400 MW
Total requested
400 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
23 June 2016
Proposed online date
June 2020

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem