Completed queue projects in the USA (2021 requests) โ€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8910.4 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

89 requests ยท page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GI-TC-2021-07, Delta County
Solar
80.0 MWOperating Delta, COWest Mar 20212024
Battery storage project 619, Owyhee County
Battery storage ยท Idaho Power Companyโ€šร„รฎPower Supply
80.0 MWOperating Owyhee, IDWest Oct 20212023
Dogfish BESS
Battery storage ยท Dogfish ESS Assets, LLC
78.2 MWOperating Pecos, TXERCOT Mar 20212025
Solar project 295, Gilchrist County
Solar ยท Duke Energy Florida, LLC
74.9 MWOperating Gilchrist, FLSoutheast Sep 20212024
Solar project 422, Manatee County
Solar ยท FPL
74.5 MWOperating Manatee, FLSoutheast May 20212025
Solar project 424C, Madison County
Solar ยท FPL
74.5 MWOperating Madison, FLSoutheast Aug 20212024
House Mountain
Other ยท House Mountain LLC
63.0 MWOperating Brewster, TXERCOT Jan 20212023
Lower Rio BESS
Battery storage ยท VESI 38 LLC
60.4 MWOperating ERCOT Feb 20212025
Cross Trails Storage
Battery storage ยท Cross Trails Energy Storage Project, LLC
58.3 MWOperating Scurry, TXERCOT Nov 20212025
Gransolar Texas One
Solar ยท Gransolar Texas One, LLC
50.8 MWOperating Milam, TXERCOT Mar 20212024
Teco GTG2
Gas ยท Thermal Energy Corp.
50.0 MWOperating Harris, TXERCOT Nov 20212024
Battery storage project SP102
Battery storage
43.9 MWOperating AZWest Jun 2021target 2023
Solar project GI-TC-2021-04, Las Animas County
Solar
40.0 MWOperating Las Animas, COWest Mar 20212024
Battery storage project SP101, Yuma County
Battery storage
35.0 MWOperating Yuma, AZWest Jan 2021target 2022
Solar project 419A, Bay County
Solar ยท FPL
24.5 MWOperating Bay, FLSoutheast Jan 20212023
Hydro project 402, Lewis And Clark County
Hydro
21.6 MWOperating Lewis And Clark, MTWest Jan 20212021
Bastrop Energy Center AGP repower Phase II
Gas
21.0 MWOperating Bastrop, TXERCOT Apr 20212022
Bastrop Energy Center AGP repower Phase I
Gas
21.0 MWOperating Bastrop, TXERCOT Apr 20212022
Cascade Energy Storage Expansion
Battery storage
20.3 MWOperating San Joaquin, CACAISO May 2021target 2022
Gas project 610, Payette County
Gas ยท Idaho Power Companyโ€šร„รฎPower Supply
20.0 MWOperating Payette, IDWest Jun 20212022
Anchor Wind IV
Onshore wind
19.3 MWOperating Eastland, TXERCOT Dec 20212024
Battery storage project Q395, Yavapai County
Battery storage
19.0 MWOperating Yavapai, AZWest Sep 2021target 2023
Solar project 411, Spink County
Solar
15.0 MWOperating Spink, SDWest May 20212021
Berlin Energy Uprate and Battery Addition
Other
15.0 MWOperating Coos, NHISO-NE Mar 2021target 2023
Solar project GEN-2021-SR9, Jackson County
Solar
10.0 MWOperating Jackson, MOSPP Aug 20212023
Rumford Uprate and Battery addition
Other
8.5 MWOperating Oxford, MEISO-NE Mar 2021target 2023
Solar project 77
Solar
8.0 MWOperating Southeast Jun 20212022
Bonny Eagle Energy Storage - Uprate
Other
8.0 MWOperating York, MEISO-NE Mar 2021target 2023
Gas project 621, Elmore County
Gas ยท Idaho Power Companyโ€šร„รฎPower Supply
7.0 MWOperating Elmore, IDWest Oct 20212023
Ebony Energy Storage Repowering
Battery storage
5.0 MWOperating Comal, TXERCOT Feb 20212025
Chula Vista Energy Center Expansion
Gas
2.8 MWOperating San Diego, CACAISO Mar 20212022
Hydro project 597, Adams County
Hydro ยท Hydroland Omega, LLC
2.4 MWOperating Adams, IDWest Apr 2021target 2021
Gas project 414, Beadle County
Gas
2.2 MWOperating Beadle, SDWest Aug 20212021
13665 Felt Road Solar
Solar + storage
2.0 MWOperating Oxford, MEISO-NE Aug 2021target 2024
Hydro project 606, Lincoln County
Hydro ยท Arkoosh Hydro Inc
1.1 MWOperating Lincoln, IDWest Jun 2021target 2021
Hydro project 599, Lincoln County
Hydro ยท Arkoosh Hydro Inc
1.0 MWOperating Lincoln, IDWest Jan 2021target 2021
Onshore wind project 410, Cascade County
Onshore wind
0.7 MWOperating Cascade, MTWest May 20212021
Hydro project 598, Canyon County
Hydro ยท Reynolds Irrigation District
0.3 MWOperating Canyon, IDWest Apr 2021target 2021
Hydro project 615, Gooding County
Hydro ยท Von Alan Industries
0.3 MWOperating Gooding, IDWest Aug 2021target 2021
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)