Solar project 77

Solar project 77 is a 8.0 MW solar request built and operating in the Southeast interconnection queue, connecting to Tampa Electric Company.

Queue statusOperating
  1. PlanningQueued Jun 2021 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
77
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tampa Electric Company
Connection point (POI)
Big Bend Substation, Hillsborough County
Technology
Solar: 8.0 MW
Total requested
8.0 MW
Service type
Network resource (NRIS)
Study phase
Interconnection Agreement Executed
Queue status
Operational
Entered queue
2 June 2021
Proposed online date
December 2022
Came online
December 2022

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in Β· Transmission lines in