SOLAR · WESTSolar project GI-TC-2021-07, Delta County
Solar project GI-TC-2021-07, Delta County is a 80.0 MW solar request built and operating in the West interconnection queue, in Delta County, Colorado, connecting to Tri-State Generation and Transmission Association.
Request details
- Queue ID
- GI-TC-2021-07
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Tri-State Generation and Transmission Association
- Connection point (POI)
- Garnet Mesa 115kV Substation
- Location
- Delta County, Colorado
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 15 March 2021
- Agreement signed
- 1 May 2024
- Proposed online date
- May 2024
- Came online
- May 2024
Location
Marker shows the centre of Delta County; the queue data does not give exact sites.
Other requests in Delta County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem