United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Texas (2020 requests) — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown11528.9 GW
Active in queue28.9 GW115 requests
Agreement signed14.9 GW54 requests
Withdrawn558,621 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

115 requests · page 2 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
BRP Volans BESS
Battery storage · BRP Volans BESS LLC
207 MWIn study Winkler, TXERCOT Aug 2020target 2027
BRP Pyxis BESS
Battery storage · BRP Pyxis BESS LLC
207 MWIn study Ward, TXERCOT Sep 2020target 2028
Sepik BESS
Battery storage · BRP Sepik BESS LLC
205 MWIn study Mitchell, TXERCOT Dec 2020target 2028
Solar project J1760, Liberty County
Solar
205 MWAgreement signed Liberty, TXMISO Jun 2020target 2023
Nockenut Springs Solar 2
Solar · Pecan Springs Energy, LLC
203 MWAgreement signed Guadalupe, TXERCOT Sep 2020target 2029
Nockenut Springs Solar 1
Solar · Pecan Springs Energy, LLC
203 MWAgreement signed Guadalupe, TXERCOT Sep 2020target 2029
Kinenos Solar
Solar · Encino del Sol Energy, LLC
203 MWIn study Brooks, TXERCOT Dec 2020target 2026
Loma Pinta Solar
Solar · Loma Pinta Wind Energy, LLC
203 MWIn study La Salle, TXERCOT Jun 2020target 2027
Samson Solar 2
Solar · Samson Solar Energy II LLC
203 MWAgreement signed Lamar, TXERCOT Jan 2020target 2026
BRP Kabru BESS
Battery storage · BRP Kabru BESS LLC
203 MWIn study Andrews, TXERCOT Oct 2020target 2028
BRP Kamet BESS
Battery storage · BRP Kamet BESS LLC
203 MWIn study Andrews, TXERCOT Oct 2020target 2025
BRP Perseus BESS
Battery storage · BRP Perseus BESS LLC
203 MWIn study Nueces, TXERCOT Aug 2020target 2027
Erin Solar
Solar · Erin Solar LLC
203 MWAgreement signed Wharton, TXERCOT Jul 2020target 2028
Bottom Grass BESS
Solar + storage · Bottom Grass Solar Project, LLC
202 MWAgreement signed Colorado, TXERCOT Nov 2020target 2028
Donegal Solar
Solar · HE-Cottonwood Solar LLC
202 MWAgreement signed Dickens, TXERCOT Oct 2020target 2028
Soda Lake Solar 2 SLF
Solar + storage · Crane II Solar Electric, LLC
202 MWAgreement signed Crane, TXERCOT Sep 2020target 2027
Nockenut Springs Solar 3
Solar · Pecan Springs Energy, LLC
201 MWIn study Gonzales, TXERCOT Sep 2020target 2029
BRP Pictor BESS
Battery storage · BRP Pictor BESS LLC
201 MWIn study Crane, TXERCOT Jul 2020target 2025
Morrow Lake Storage
Solar + storage · Morrow Lake Storage, LLC
201 MWIn study Frio, TXERCOT Feb 2020target 2026
Ramsey Storage
Battery storage · Hecate Energy Ramsey Storage LLC
201 MWAgreement signed Wharton, TXERCOT May 2020target 2027
Elbus BESS
Battery storage · BRP Elbus BESS LLC
201 MWIn study Caldwell, TXERCOT Dec 2020target 2028
Clutch City Solar Phase I
Solar · HZ Solar I, LLC
201 MWAgreement signed Brazoria, TXERCOT Jan 2020target 2028
Battery storage project GEN-2020-081, Rusk County
Battery storage
200 MWAgreement signed Rusk, TXSPP Apr 2020target 2028
Stem Solar
Solar · Innovative Solar 134, LLC
200 MWIn study Swisher, TXERCOT Feb 2020target 2025
Battery storage project GEN-2020-060, Lubbock County
Battery storage
200 MWIn study Lubbock, TXSPP Apr 2020target 2027
Accalia Point Solar
Solar · Accalia Point Solar LLC
191 MWIn study Cameron, TXERCOT Oct 2020target 2029
Crowded Star Solar II
Solar + storage · Jones City Solar II, LLC
190 MWAgreement signed Jones, TXERCOT Mar 2020target 2026
Lan Solar SLF
Solar + storage · BR Solar, LLC
182 MWIn study Lamar, TXERCOT May 2020target 2028
Yellow Viking Solar
Solar · Yellow Viking Development One, LLC
171 MWAgreement signed Somervell, TXERCOT Oct 2020target 2027
Creekfield Solar
Solar
161 MWPaused / redesign Fort Bend, TXERCOT Jan 2020
Bowstring BESS
Battery storage · Longbow Energy Storage, LLC
155 MWAgreement signed San Patricio, TXERCOT Nov 2020target 2028
Anson BAT
Solar + storage · Anson II Storage LLC
154 MWAgreement signed Jones, TXERCOT Dec 2020target 2027
Pink Solar
Solar · Pink Solar, LLC
152 MWAgreement signed Hunt, TXERCOT Jan 2020target 2027
Stockyard Grid Batt
Battery storage · Stockyard Grid, LLC
151 MWAgreement signed Tarrant, TXERCOT Jan 2020target 2026
Solar project J1671, Walker County
Solar
150 MWUnder construction Walker, TXMISO Jun 2020target 2025
Noria Solar DCC
Solar
145 MWPaused / redesign Nueces, TXERCOT Aug 2020target 2025
Starling Solar
Solar + storage · Starling Solar, LLC
144 MWAgreement signed Gonzales, TXERCOT Jun 2020target 2028
BRP Octans BESS
Battery storage · BRP OCTANS BESS LLC
130 MWIn study Pecos, TXERCOT Jul 2020target 2029
Shaw Solar
Solar · Rio Lago Solar, LLC
125 MWAgreement signed Bandera, TXERCOT Oct 2020target 2026
BRP Ampato BESS
Battery storage · BRP Ampato BESS LLC
122 MWIn study Crane, TXERCOT Aug 2020target 2027
Caney Creek Solar
Solar · HEP Aquamarine Holdings LLC
121 MWAgreement signed Van Zandt, TXERCOT Sep 2020target 2027
Kalina Solar
Solar · Aurora Solar LLC
120 MWIn study San Patricio, TXERCOT Aug 2020target 2029
Razorbill Storage
Solar + storage · RWE Solar Development, LLC
120 MWIn study Matagorda, TXERCOT Aug 2020target 2027
Atria Solar
Solar · Atria Energy Project, LLC
112 MWIn study Chambers, TXERCOT Oct 2020target 2025
Photon Solar 3 SLF
Solar · GulfStar Power, LLC
110 MWAgreement signed Wharton, TXERCOT Oct 2020target 2026
McClure Solar
Solar · McClure Solar LLC
106 MWIn study Palo Pinto, TXERCOT Jun 2020target 2025
Estonian Storage
Other · 249RD 8ME
103 MWPaused / redesign Delta, TXERCOT Jan 2020target 2022
Blue Sky Sol
Solar + storage · Blue Sky Solar LLC
101 MWAgreement signed Crockett, TXERCOT Dec 2020target 2027
Matagorda Solar
Solar · Matagorda Solar Farm, LLC
101 MWAgreement signed Matagorda, TXERCOT May 2020target 2027
Inertia BESS 2
Battery storage
101 MWPaused / redesign Haskell, TXERCOT Oct 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)