πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in PJM (Mid-Atlantic, Midwest) (2023 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown15614.6 GW
Active in queue14.6 GW156 requests
Agreement signed0.0 MW0 requests
Withdrawn11867 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

156 requests Β· page 2 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project AI2-163, Mclean County
Onshore wind
68.8 MWIn study Mclean, ILPJM Mar 2023target 2025
Battery storage project AI2-307, Cecil County
Battery storage
60.5 MWIn study Cecil, MDPJM Mar 2023target 2026
Battery storage project AI2-231A, Botetourt County
Battery storage
60.0 MWIn study Botetourt, VAPJM Mar 2023target 2023
Solar + storage project AI2-444
Solar + storage
59.5 MWIn study WVPJM Mar 2023target 2026
Solar project AI2-245, Woodford County
Solar
55.2 MWIn study Woodford, ILPJM Mar 2023target 2028
Solar project AI2-224, Charlotte County
Solar
55.0 MWIn study Charlotte, VAPJM Mar 2023target 2025
Solar project AI2-196, Lycoming County
Solar
51.5 MWIn study Lycoming, PAPJM Mar 2023target 2025
Solar project AI2-244, Nottoway County
Solar
50.3 MWIn study Nottoway, VAPJM Mar 2023target 2028
Battery storage project AJ1-001, Mecklenburg County
Battery storage
50.0 MWIn study Mecklenburg, VAPJM Apr 2023target 2028
Battery storage project AI2-042, Louisa County
Battery storage
50.0 MWIn study Louisa, VAPJM Feb 2023target 2026
Solar project AI2-416, Augusta County
Solar
50.0 MWIn study Augusta, VAPJM Mar 2023target 2026
Solar + storage project AI2-030, Adams County
Solar + storage
50.0 MWIn study Adams, OHPJM Jan 2023target 2024
Solar project AJ1-022, Mecklenburg County
Solar
49.0 MWIn study Mecklenburg, VAPJM Jun 2023target 2027
Solar project AI2-161, Vermillion County
Solar
48.0 MWIn study Vermillion, INPJM Mar 2023target 2025
Solar project AI2-151, Logan County
Solar
48.0 MWIn study Logan, ILPJM Feb 2023target 2025
Solar project AI2-162, Whitley County
Solar
48.0 MWIn study Whitley, INPJM Mar 2023target 2025
Solar project AI2-417, Dekalb County
Solar
48.0 MWIn study Dekalb, ILPJM Mar 2023target 2026
Battery storage project AI2-277, Greensville County
Battery storage
45.0 MWIn study Greensville, VAPJM Mar 2023target 2026
Solar project AI2-150, Huntington County
Solar
44.4 MWIn study Huntington, INPJM Feb 2023target 2025
Solar project AI2-159, Miami County
Solar
43.5 MWIn study Miami, OHPJM Mar 2023target 2027
Solar project AI2-421, Dekalb County
Solar
43.2 MWIn study Dekalb, INPJM Mar 2023target 2027
Solar project AI2-426, Allen County
Solar
43.2 MWIn study Allen, INPJM Mar 2023target 2027
Solar project AI2-079, Fauquier County
Solar
40.7 MWIn study Fauquier, VAPJM Feb 2023target 2025
Solar project AI2-060, Henry County
Solar
40.7 MWIn study Henry, ILPJM Feb 2023target 2024
Solar project AI2-475, Montour County
Solar
40.6 MWIn study Montour, PAPJM Mar 2023target 2026
Solar project AI2-333, Pike County
Solar
40.0 MWIn study Pike, KYPJM Mar 2023target 2026
Solar project AI2-332, Nicholas County
Solar
40.0 MWIn study Nicholas, WVPJM Mar 2023target 2030
Solar project AI2-425, Huntington County
Solar
40.0 MWIn study Huntington, INPJM Mar 2023target 2028
Solar + storage project AJ1-018, Worcester County
Solar + storage
39.0 MWIn study Worcester, MDPJM Jun 2023target 2028
Solar project AI2-144, St. Joseph County
Solar
36.0 MWIn study St. Joseph, MIPJM Feb 2023target 2025
Solar project AI2-335, Martin County
Solar
34.9 MWIn study Martin, KYPJM Mar 2023target 2026
Solar project AI2-334, Martin County
Solar
34.9 MWIn study Martin, KYPJM Mar 2023target 2026
Solar project AI2-474, Montour County
Solar
34.8 MWIn study Montour, PAPJM Mar 2023target 2026
Solar project AI2-336, Harrison County
Solar
34.6 MWIn study Harrison, OHPJM Mar 2023target 2026
Battery storage project AJ1-038, York County
Battery storage
33.0 MWIn study York, VAPJM Jun 2023target 2025
Solar project AI2-153, Louisa County
Solar
32.0 MWIn study Louisa, VAPJM Mar 2023target 2022
Solar project AI2-145, Montgomery County
Solar
30.4 MWIn study Montgomery, VAPJM Feb 2023target 2022
Solar project AI2-337, Madison County
Solar
30.0 MWIn study Madison, OHPJM Mar 2023target 2023
Battery storage project AI2-278, Lancaster County
Battery storage
30.0 MWIn study Lancaster, VAPJM Mar 2023target 2027
Battery storage project AI2-311, Washington County
Battery storage
30.0 MWIn study Washington, MDPJM Mar 2023target 2025
Battery storage project AI2-227, Amherst County
Battery storage
30.0 MWIn study Amherst, VAPJM Mar 2023target 2023
Solar project AI2-471, Montour County
Solar
29.5 MWIn study Montour, PAPJM Mar 2023target 2025
Solar project AI2-338, Charles City County
Solar
29.2 MWIn study Charles City, VAPJM Mar 2023target 2024
Solar project AI2-473, Montour County
Solar
29.0 MWIn study Montour, PAPJM Mar 2023target 2026
Solar project AI2-152, Madison County
Solar
28.8 MWIn study Madison, INPJM Mar 2023target 2025
Solar project AI2-410, Dekalb County
Solar
28.5 MWIn study Dekalb, ILPJM Mar 2023target 2026
Solar project AI2-424, Huntington County
Solar
28.0 MWIn study Huntington, INPJM Mar 2023target 2028
Solar project AI2-339, Nicholas County
Solar
26.8 MWIn study Nicholas, WVPJM Mar 2023target 2024
Solar project AI2-427, Licking County
Solar
26.4 MWIn study Licking, OHPJM Mar 2023target 2027
Onshore wind project AI2-400, Bureau County
Onshore wind
25.0 MWIn study Bureau, ILPJM Mar 2023target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)