Withdrawn queue requests in the USA (2020 requests) — page 17

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,752246.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,752 requests · page 17 of 36
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-883, Early County
Solar
80.0 MWWithdrawn / abandoned Early, GASoutheast Jul 2020target 2023
Solar + storage project IC-885, Dallas County
Solar + storage
80.0 MWWithdrawn / abandoned Dallas, ALSoutheast Jul 2020target 2024
Honey Ridge Solar
Solar · Honey Ridge Solar 1
80.0 MWWithdrawn / abandoned Jefferson, NYNYISO Aug 2020
Battery storage project AF2-183, Lee County
Battery storage · Deriva Energy Solar, LLC
80.0 MWWithdrawn / abandoned Lee, ILPJM Mar 2020target 2022
Solar project J1645, Renville County
Solar
80.0 MWWithdrawn / abandoned Renville, MNMISO Jun 2020target 2023
Solar + storage project AG1-502, Orange County
Solar + storage · Oak Green Solar LLC
80.0 MWWithdrawn / abandoned Orange, VAPJM Sep 2020target 2023
Solar project IC-916, Houston County
Solar
80.0 MWWithdrawn / abandoned Houston, ALSoutheast Nov 2020
Solar + storage project IC-917, Houston County
Solar + storage
80.0 MWWithdrawn / abandoned Houston, ALSoutheast Nov 2020
Solar project 462, Lawrence County
Solar
80.0 MWWithdrawn / abandoned Lawrence, TNSoutheast Dec 2020
Solar project AG1-249, Union County
Solar
80.0 MWWithdrawn / abandoned Union, OHPJM Sep 2020target 2023
Battery storage project AG1-268, Essex County
Battery storage
80.0 MWWithdrawn / abandoned Essex, NJPJM Sep 2020target 2022
Cannon Solar SLF
Solar · Cannon Solar, LLC
80.0 MWWithdrawn / abandoned ERCOT Sep 2020target 2027
Solar project 20-086, Morrow County
Solar
80.0 MWWithdrawn / abandoned Morrow, ORWest May 2020target 2023
Solar + storage project IC-886, Houston County
Solar + storage
80.0 MWWithdrawn / abandoned Houston, ALSoutheast Jul 2020target 2024
Solar + storage project IC-924, Baldwin County
Solar + storage
80.0 MWWithdrawn / abandoned Baldwin, ALSoutheast Dec 2020target 2025
Solar + storage project IC-937, Chambers County
Solar + storage
80.0 MWWithdrawn / abandoned Chambers, ALSoutheast Dec 2020target 2024
Solar project AF2-066, Preble County
Solar
80.0 MWWithdrawn / abandoned Preble, OHPJM Jan 2020target 2022
Solar project AF2-242, Beaufort County
Solar
80.0 MWWithdrawn / abandoned Beaufort, NCPJM Mar 2020target 2023
Sedge Hill Solar
Solar · Sedge Hill Solar, LLC
80.0 MWWithdrawn / abandoned Halifax, VAPJM Mar 2020target 2022
Solar project AG2-017, Shelby County
Solar
80.0 MWWithdrawn / abandoned Shelby, KYPJM Oct 2020target 2022
Solar project 79, Pima County
Solar
80.0 MWWithdrawn / abandoned Pima, AZWest Mar 2020target 2022
Solar project 90, Kittitas County
Solar
80.0 MWWithdrawn / abandoned Kittitas, WAWest Aug 2020target 2023
Kce NY 19
Battery storage · KCE NY 19 LLC
80.0 MWWithdrawn / abandoned Orange, NYNYISO Jan 2020
NYC Energy BNY Phase 1
Battery storage · NYC Energy
79.9 MWWithdrawn / abandoned Kings, NYNYISO Apr 2020
Solar project 373, Carbon County
Solar
79.8 MWWithdrawn / abandoned Carbon, MTWest Feb 2020target 2023
Suffolk BESS
Battery storage · Suffolk BESS LLC
79.7 MWWithdrawn / abandoned Suffolk, NYNYISO Mar 2020
Onshore wind project AF2-128, Lasalle County
Onshore wind · UKA Green Power LLC
79.5 MWWithdrawn / abandoned Lasalle, ILPJM Feb 2020target 2024
Onshore wind project 1223, Carbon County
Onshore wind
79.4 MWWithdrawn / abandoned Carbon, WYWest Apr 2020target 2021
Solar + storage project AG1-194, Fayette County
Solar + storage · Keeneys Creek Solar I, LLC
79.0 MWWithdrawn / abandoned Fayette, WVPJM Sep 2020target 2023
Solar project IC-899, Stone County
Solar
78.0 MWWithdrawn / abandoned Stone, MSSoutheast Aug 2020target 2024
Solar project IC-898, Stone County
Solar
78.0 MWWithdrawn / abandoned Stone, MSSoutheast Aug 2020
Polvadero Hybrid Solar
Solar + storage
76.9 MWWithdrawn / abandoned Fresno, CACAISO Apr 2020target 2023
Suffolk County Storage II
Battery storage · Suffolk County Energy Storage II
76.8 MWWithdrawn / abandoned Suffolk, NYNYISO May 2020
Solar
Solar
76.3 MWWithdrawn / abandoned Merrimack, NHISO-NE Aug 2020target 2025
Solar + storage project IC-902, Emanuel County
Solar + storage
76.0 MWWithdrawn / abandoned Emanuel, GASoutheast Aug 2020target 2023
BRP Galan BESS
Battery storage · BRP Galan BESS LLC
76.0 MWWithdrawn / abandoned ERCOT Aug 2020target 2027
SBranch Expansion Solar
Solar · CG Wharton County LLC
76.0 MWWithdrawn / abandoned Wharton, TXERCOT Oct 2020target 2022
Solar project GEN-2021-003, Richland County
Solar
75.5 MWWithdrawn / abandoned Richland, MTSPP Dec 20202024
Solar + storage project Q328, Pinal County
Solar + storage
75.0 MWWithdrawn / abandoned Pinal, AZWest Mar 2020target 2022
Solar project AG1-441, Mecklenburg County
Solar · RWE Solar Development, LLC
75.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Sep 2020target 2023
Battery storage project AF2-113, Clinton County
Battery storage
75.0 MWWithdrawn / abandoned Clinton, OHPJM Feb 2020target 2022
Battery storage project J1683, Porter County
Battery storage
75.0 MWWithdrawn / abandoned Porter, INMISO Jun 2020target 2023
Solar project J1735, Rock County
Solar
75.0 MWWithdrawn / abandoned Rock, WIMISO Jun 2020target 2025
Solar project J1597, Wadena County
Solar
75.0 MWWithdrawn / abandoned Wadena, MNMISO Jun 2020target 2023
Solar + storage project AG1-219, Fayette County
Solar + storage · Fayette Solar I, LLC
75.0 MWWithdrawn / abandoned Fayette, WVPJM Sep 2020target 2023
Battery storage project AG1-537, Augusta County
Battery storage · Chestnut Storage, LLC
75.0 MWWithdrawn / abandoned Augusta, VAPJM Sep 2020target 2024
Solar project AF2-324, Edgecombe County
Solar · Bridge Solar, LLC
75.0 MWWithdrawn / abandoned Edgecombe, NCPJM Mar 2020target 2022
Solar project AF2-385, Sussex County
Solar
75.0 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2022
Solar project AF2-328, Pike County
Solar
75.0 MWWithdrawn / abandoned Pike, KYPJM Mar 2020target 2023
Solar + storage project Q331, Maricopa County
Solar + storage
75.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2020target 2022
Page 17 of 36

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)