NYC Energy BNY Phase 1

NYC Energy BNY Phase 1 is a 79.9 MW battery storage request withdrawn in the NYISO interconnection queue, in Kings County, New York, connecting to ConEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedDec 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1006
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
NYC Energy
Connection point (POI)
Hudson Ave Substation
Location
Kings County, New York
Technology
Battery: 79.9 MW
Total requested
79.9 MW
Queue status
Withdrawn
Entered queue
20 April 2020
Withdrawn
December 2020

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.