Solar project GEN-2021-003, Richland County

Solar project GEN-2021-003, Richland County is a 75.5 MW solar request withdrawn in the SPP interconnection queue, in Richland County, Montana, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2020 (completed)
  2. Withdrawn / abandonedJul 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2024 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-003
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Fairview 115kV Substation
Location
Richland County, Montana
Technology
Solar: 75.5 MW
Total requested
75.5 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
11 December 2020
Proposed online date
December 2024
Came online
December 2024
Withdrawn
July 2023

Location

Marker shows the centre of Richland County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Richland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem