SOLAR + STORAGE Β· WEST

Solar + storage project Q331, Maricopa County

Solar + storage project Q331, Maricopa County is a 75.0 MW solar + storage request withdrawn in the West interconnection queue, in Maricopa County, Arizona, connecting to Arizona Public Service.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q331
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Saddle Mountain 69kV
Location
Maricopa County, Arizona
Technology
Solar: 75.0 MW Β· Battery
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
23 March 2020
Proposed online date
June 2022

Location

Marker shows the centre of Maricopa County; the queue data does not give exact sites.

Power plants in Arizona Β· Transmission lines in Arizona

Other requests in Maricopa County