United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in PJM (Mid-Atlantic, Midwest) — page 17

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown905105.4 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

905 requests · page 17 of 19
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AI2-483, Licking County
Battery storage
13.4 MWIn study Licking, OHPJM Mar 2023target 2025
Battery storage project AI2-318, Gloucester County
Battery storage
12.8 MWIn study Gloucester, VAPJM Mar 2023target 2025
Solar project AG2-626, Warren County
Solar · Chamberlain East Solar Farm LLC
12.5 MWIn study Warren, NJPJM Feb 2025target 2021
Solar project AI2-414, Berks County
Solar
12.5 MWIn study Berks, PAPJM Mar 2023target 2026
Solar project AI2-422, Jay County
Solar
12.0 MWIn study Jay, INPJM Mar 2023target 2027
Solar project AI2-404, Hart County
Solar
12.0 MWIn study Hart, KYPJM Mar 2023target 2025
Solar project AH2-157, Somerset County
Solar
12.0 MWIn study Somerset, PAPJM Mar 2022target 2025
Solar project AI2-412, Whitley County
Solar
12.0 MWIn study Whitley, INPJM Mar 2023target 2026
Solar project AI2-423, Jay County
Solar
12.0 MWIn study Jay, INPJM Mar 2023target 2027
Solar project AH2-189, Susquehanna County
Solar
12.0 MWIn study Susquehanna, PAPJM Mar 2022target 2025
Solar project AH2-190, Somerset County
Solar
12.0 MWIn study Somerset, PAPJM Mar 2022target 2025
Solar project AI2-413, Whitley County
Solar
12.0 MWIn study Whitley, INPJM Mar 2023target 2026
Solar project AI2-182, Preston County
Solar
12.0 MWIn study Preston, WVPJM Feb 2023target 2025
Solar project AH1-396, Lunenburg County
Solar · Ameresco Inc
11.9 MWIn study Lunenburg, VAPJM Feb 2025target 2023
Solar project AI2-350, Queen Anne's County
Solar
11.9 MWIn study Queen Anne's, MDPJM Mar 2023target 2025
Solar project AH2-040, Tucker County
Solar
11.5 MWIn study Tucker, WVPJM Nov 2021target 2024
Solar project AG2-262, Halifax County
Solar · Staunton Solar LLC
11.0 MWIn study Halifax, VAPJM Feb 2025target 2023
Solar project AI2-349, Marion County
Solar
11.0 MWIn study Marion, KYPJM Mar 2023target 2029
Solar project AI2-430, Dekalb County
Solar
11.0 MWIn study Dekalb, INPJM Mar 2023target 2023
Solar project AH2-038, Hancock County
Solar
10.8 MWIn study Hancock, WVPJM Nov 2021target 2024
Other project AH2-007, Fayette County
Other
10.1 MWIn study Fayette, OHPJM Oct 2021target 2024
Other project AH1-661, Muskingum County
Other · Tallgrass Muskingum Community Power, LLC
10.1 MWIn study Muskingum, OHPJM Feb 2025target 2023
Solar + storage project AH2-384, Martin County
Solar + storage
10.0 MWIn study Martin, NCPJM Mar 2022target 2026
Solar project AI1-126, Cumberland County
Solar
10.0 MWIn study Cumberland, VAPJM Sep 2022target 2024
Solar project AH2-137, Amherst County
Solar
10.0 MWIn study Amherst, VAPJM Feb 2022target 2026
Battery storage project AH2-205, Cook County
Battery storage
10.0 MWIn study Cook, ILPJM Mar 2022target 2026
Solar project AG2-166, Cumberland County
Solar · Costen Solar, Inc
10.0 MWIn study Cumberland, PAPJM Jan 2025target 2023
Aurora Battery Storage
Battery storage
10.0 MWPaused / redesign Will, ILPJM Oct 2020target 2028
Solar project AH1-348, Wise County
Solar · Highlands CF Solar, LLC
10.0 MWIn study Wise, VAPJM Mar 2025target 2023
SunEast Hooversville Solar
Solar
10.0 MWPaused / redesign Somerset, PAPJM Oct 2019target 2026
Solar project AG2-057, Morrow County
Solar · Crossroads Solar I, LLC
10.0 MWIn study Morrow, OHPJM Apr 2025target 2022
Solar project AH2-320, Cambria County
Solar
10.0 MWIn study Cambria, PAPJM Mar 2022target 2024
NJ Land Phase II
Solar
10.0 MWPaused / redesign Burlington, NJPJM Mar 2020target 2025
Other project AI2-025, New Castle County
Other
10.0 MWIn study New Castle, DEPJM Dec 2022target 2026
Solar project AH2-064, Beaver County
Solar
10.0 MWIn study Beaver, PAPJM Dec 2021target 2023
Battery storage project AH2-206, Cook County
Battery storage
10.0 MWIn study Cook, ILPJM Mar 2022target 2026
Solar + storage project AI1-106, Halifax County
Solar + storage
9.9 MWIn study Halifax, VAPJM Aug 2022target 2023
Solar project AH1-399, Hanover County
Solar · Ameresco Inc
9.9 MWIn study Hanover, VAPJM Feb 2025target 2023
Solar + storage project AI1-114, Cambria County
Solar + storage
9.9 MWIn study Cambria, PAPJM Sep 2022target 2025
Solar + storage project AI1-115, Clearfield County
Solar + storage
9.9 MWIn study Clearfield, PAPJM Sep 2022target 2025
Solar project AI2-398, Preble County
Solar
9.6 MWIn study Preble, OHPJM Mar 2023target 2026
Scout Storage I
Battery storage
9.0 MWPaused / redesign Accomack, VAPJM Jan 2020target 2026
Solar project AH1-054, Ocean County
Solar · Pasadena Pemberton Solar Farm, LLC
8.3 MWIn study Ocean, NJPJM Feb 2025target 2022
Solar project AI1-033, Somerset County
Solar
8.0 MWIn study Somerset, NJPJM Apr 2022target 2026
Solar project AH2-128, Clarion County
Solar
8.0 MWIn study Clarion, PAPJM Feb 2022target 2026
Solar project AH2-412, Cumberland County
Solar
7.4 MWIn study Cumberland, NJPJM Mar 2022target 2022
Solar project AI2-310, Venango County
Solar
7.3 MWIn study Venango, PAPJM Mar 2023target 2025
Maryland Offshore Wind Energy Project (MOWEP)
Offshore wind
7.3 MWPaused / redesign Sussex, DEPJM Apr 2019target 2027
Solar project AH1-057, Wicomico County
Solar · Kumquat & Citron Cleantech LLC
7.2 MWIn study Wicomico, MDPJM Mar 2025target 2023
Barbertown Solar
Solar
7.0 MWPaused / redesign Hunterdon, NJPJM Mar 2020target 2026
Page 17 of 19

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)