United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2010 requests) โ page 16
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project W3-168, Adams County Solar |
15.0 MW | Withdrawn / abandoned |
| Turning Point Solar Solar |
15.0 MW | Withdrawn / abandoned |
| Bio Verde PV - Kettleman 1 Solar |
15.0 MW | Withdrawn / abandoned |
| Solar project W3-087, Kent County Solar |
15.0 MW | Withdrawn / abandoned |
| Stewartsville Solar Farm Solar |
15.0 MW | Withdrawn / abandoned |
| Wind Onshore wind |
14.9 MW | Withdrawn / abandoned |
| Turning Point Solar Solar |
14.9 MW | Withdrawn / abandoned |
| East Lancaster Power Plant Solar |
14.0 MW | Withdrawn / abandoned |
| Onshore wind project 345-A, Washington County Onshore wind |
14.0 MW | Withdrawn / abandoned |
| Peabody Jac Solar |
14.0 MW | Withdrawn / abandoned |
| Other project J149, Wayne County Other |
13.6 MW | Withdrawn / abandoned |
| East Windsor Solar Farm Solar |
13.0 MW | Withdrawn / abandoned |
| Other project W3-161, Fayette County Other |
13.0 MW | Withdrawn / abandoned |
| Three Rocks Solar Solar |
13.0 MW | Withdrawn / abandoned |
| Solar project V4-077, Mifflin County Solar |
13.0 MW | Withdrawn / abandoned |
| Solar project W3-071, Worcester County Solar |
12.5 MW | Withdrawn / abandoned |
| Dresden Island Lock & Dam Hydro |
12.1 MW | Withdrawn / abandoned |
| Other project W2-062, Perry County Other |
12.1 MW | Withdrawn / abandoned |
| Solar project Q161, Yuma County Solar |
12.0 MW | Withdrawn / abandoned |
| Solar project Q149, Yavapai County Solar |
12.0 MW | Withdrawn / abandoned |
| Solar project W3-170, Putnam County Solar |
12.0 MW | Withdrawn / abandoned |
| Solar project W3-169, Adams County Solar |
12.0 MW | Withdrawn / abandoned |
| Sepv-15 Solar |
12.0 MW | Withdrawn / abandoned |
| Ohio Solar I Solar |
12.0 MW | Withdrawn / abandoned |
| Solar project W1-125, Salem County Solar |
12.0 MW | Withdrawn / abandoned |
| Monmouth West Solar I Solar |
12.0 MW | Withdrawn / abandoned |
| Solar project W3-055, Burlington County Solar |
12.0 MW | Withdrawn / abandoned |
| Des Solar |
11.8 MW | Withdrawn / abandoned |
| Onshore wind project 359, Lincoln County Onshore wind |
11.5 MW | Withdrawn / abandoned |
| Repowered Mckittrick Cogen Plant Gas |
11.2 MW | Withdrawn / abandoned |
| Solar project V4-055, Meigs County Solar |
11.0 MW | Withdrawn / abandoned |
| Solar project W3-081, Hunterdon County Solar |
11.0 MW | Withdrawn / abandoned |
| Other project G0434, Linn County Other |
11.0 MW | Withdrawn / abandoned |
| Brandon Road Lock & Dam Hydro |
10.6 MW | Withdrawn / abandoned |
| Rough Acres Solar Solar |
10.4 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2010-041, Richardson County Onshore wind |
10.3 MW | Withdrawn / abandoned |
| Solar project W4-020, Montgomery County Solar |
10.1 MW | Withdrawn / abandoned |
| Gombasi Solar Farm Solar |
10.0 MW | Withdrawn / abandoned |
| PV Rosina 1 SG Solar |
10.0 MW | Withdrawn / abandoned |
| Rosina Bio Verde Solar |
10.0 MW | Withdrawn / abandoned |
| Lincoln Solar Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project 320, Malheur County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project W3-009, Cumberland County Solar |
10.0 MW | Withdrawn / abandoned |
| Springfield Solar Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project W3-058, Cape May County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project W2-070, Salem County Solar |
10.0 MW | Withdrawn / abandoned |
| Keller Solar Farm Solar |
10.0 MW | Withdrawn / abandoned |
| Ringoes Solar Farm Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project W2-100, Salem County Solar |
10.0 MW | Withdrawn / abandoned |
| Gas project W1-038, Bergen County Gas |
10.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)302 ยท 22.6 GW
- PJM (Mid-Atlantic, Midwest)361 ยท 21.6 GW
- CAISO (California)168 ยท 19.1 GW
- Southeast (non-ISO utilities)18 ยท 11.1 GW
- MISO (Midcontinent)72 ยท 10.9 GW
- SPP (Southwest Power Pool)50 ยท 9,058 MW
- ERCOT (Texas)28 ยท 3,689 MW
- ISO-NE (New England)12 ยท 1,337 MW
- NYISO (New York)5 ยท 1,285 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)