🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR · CAISO

East Lancaster Power Plant

East Lancaster Power Plant is a 14.0 MW solar request withdrawn in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2010 (completed)
  2. Withdrawn / abandonedJan 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
619
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Piute-Lancaster 66kV
Location
Los Angeles County, California
Technology
Solar: 14.0 MW
Total requested
14.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
22 April 2010
Proposed online date
January 2012
Withdrawn
January 2011

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem