πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Rough Acres Solar

Rough Acres Solar is a 10.4 MW solar request withdrawn in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2010 (completed)
  2. Withdrawn / abandonedDec 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
623A
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Boulevard Sub 138 kV Bus
Location
San Diego County, California
Technology
Solar: 10.4 MW
Total requested
10.4 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
10 May 2010
Proposed online date
June 2011
Withdrawn
December 2010

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in San Diego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem