Peabody Jac is a 14.0 MW solar request withdrawn in the CAISO interconnection queue, in Solano County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2010 (completed)
  2. Withdrawn / abandonedJul 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
649A
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Dixon-Vaca #2 60kV
Location
Solano County, California
Technology
Solar: 14.0 MW
Total requested
14.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
25 October 2010
Proposed online date
March 2013
Withdrawn
July 2012

Location

Marker shows the centre of Solano County; the queue data does not give exact sites.