Requests shown1,857519.1 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,857 requests · page 16 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project IA-PNM-2025-06, Bernalillo County
Solar + storage
250 MWIn study Bernalillo, NMWest Mar 2025target 2031
Solar project S0005, Carbon County
Solar · PacifiCorp
250 MWIn study Carbon, WYWest Mar 2022target 2026
Onshore wind project G0974, Wasco County
Onshore wind
250 MWIn study Wasco, ORWest Oct 2023target 2029
Battery storage project Q278, Maricopa County
Battery storage
250 MWIn study Maricopa, AZWest Jun 2018target 2021
Solar + storage project Q378, Maricopa County
Solar + storage
250 MWPaused / redesign Maricopa, AZWest Mar 2021target 2024
Other project 86, Apache County
Other
250 MWIn study Apache, AZWest Dec 2020target 2023
Solar + storage project 21-098, Jefferson County
Solar + storage
250 MWAgreement signed Jefferson, ORWest Apr 2021target 2034
Other project 95, Apache County
Other
250 MWIn study Apache, AZWest Jun 2021target 2024
Solar + storage project Q295, Pinal County
Solar + storage
250 MWAgreement signed Pinal, AZWest Mar 2019target 2022
Solar + storage project G0676, Klickitat County
Solar + storage
250 MWIn study Klickitat, WAWest Mar 2021target 2024
Solar + storage project T2-053, Iron County
Solar + storage
248 MWIn study Iron, UTWest Sep 2025target 2029
EC500W Project
Onshore wind
247 MWAgreement signed Chaves, NMWest Jul 2017target 2020
Onshore wind project Q458, Navajo County
Onshore wind
242 MWIn study Navajo, AZWest Mar 2022target 2026
Other project 98, Pinal County
Other
241 MWIn study Pinal, AZWest Sep 2021target 2025
Solar + storage project 605, Elmore County
Solar + storage · South Bennett Solar LLC
240 MWPaused / redesign Elmore, IDWest May 2021target 2029
Solar project GI-2019-6, Pueblo County
Solar
240 MWIn study Pueblo, COWest May 20192021
Solar + storage project Company QX, Churchill County
Solar + storage
240 MWIn study Churchill, NVWest Mar 2024target 2028
Solar project S0004, Carbon County
Solar · PacifiCorp
240 MWIn study Carbon, WYWest Mar 2022target 2026
Solar + storage project 551, Elmore County
Solar + storage · Bennett Solar B LLC
240 MWPaused / redesign Elmore, IDWest Apr 2019target 2026
Solar + storage project Company HQ, Pershing County
Solar + storage
240 MWPaused / redesign Pershing, NVWest Sep 2017target 2024
Onshore wind project G0640, Klamath County
Onshore wind
239 MWIn study Klamath, ORWest Feb 2020target 2025
Onshore wind project G0435, Morrow County
Onshore wind
238 MWIn study Morrow, ORWest Aug 2010target 2013
Onshore wind project GI-2004-2, Baca County
Onshore wind
238 MWAgreement signed Baca, COWest Feb 2004
Solar + storage project GI-DISIS-2022-04, Kit Carson County
Solar + storage
237 MWAgreement signed Kit Carson, COWest May 2022target 2027
Solar project S0003, Converse County
Solar · PacifiCorp
237 MWIn study Converse, WYWest Mar 2022target 2026
Gas project IA-PNM-2017-14, San Juan County
Gas
236 MWAgreement signed San Juan, NMWest Oct 2017target 2022
Onshore wind project G1036, Hood River County
Onshore wind
234 MWIn study Hood River, ORWest Nov 2023target 2028
Onshore wind project G0683, Benton County
Onshore wind
233 MWIn study Benton, WAWest Jul 2021target 2026
Solar + storage project G0839, Jefferson County
Solar + storage
230 MWIn study Jefferson, ORWest Feb 2023target 2027
Solar + storage project G0838, Jefferson County
Solar + storage
230 MWIn study Jefferson, ORWest Feb 2023target 2027
Solar + storage project GI-2020-10, Pueblo County
Solar + storage
230 MWPaused / redesign Pueblo, COWest Apr 2020target 2023
Solar project IA-PNM-2024-04, Santa Fe County
Solar
230 MWIn study Santa Fe, NMWest Jun 2024target 2028
Geothermal project Company LM, Lyon County
Geothermal
230 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Solar + storage project 2023-G4, Mohave County
Solar + storage
225 MWIn study Mohave, AZWest Apr 2023target 2026
Solar + storage project 2022-G2, Mohave County
Solar + storage
225 MWIn study Mohave, AZWest Apr 2022target 2025
Solar project G0935, Walla Walla County
Solar
225 MWIn study Walla Walla, WAWest Sep 2023target 2027
Solar + storage project 2023-G5, Mohave County
Solar + storage
225 MWIn study Mohave, AZWest Apr 2023target 2026
Solar + storage project 2022-G5, Mohave County
Solar + storage
225 MWIn study Mohave, AZWest Apr 2022target 2025
Solar + storage project 2018-G41, Mohave County
Solar + storage
225 MWIn study Mohave, AZWest Oct 2018target 2020
Solar project GI-TC-2024-17, Kit Carson County
Solar
225 MWIn study Kit Carson, COWest May 2024target 2030
Solar + storage project G0985, Lincoln County
Solar + storage
225 MWIn study Lincoln, WAWest Nov 2023target 2027
Battery storage project T2-061, Salt Lake County
Battery storage
225 MWIn study Salt Lake, UTWest Sep 2025target 2027
Solar + storage project GI-DISIS-2022-49, Prowers County
Solar + storage
225 MWPaused / redesign Prowers, COWest May 2022target 2029
Solar + storage project IA-PNM-2025-05, Bernalillo County
Solar + storage
225 MWIn study Bernalillo, NMWest Mar 2025target 2030
Solar + storage project Q75, Kern County
Solar + storage
225 MWIn study Kern, CAWest Jan 2020target 2022
Onshore wind project GI-CS-2025-24, Kit Carson County
Onshore wind
225 MWIn study Kit Carson, COWest Sep 2025target 2029
Solar + storage project 2018-G40, Mohave County
Solar + storage
225 MWIn study Mohave, AZWest Oct 2018target 2020
Solar + storage project G0598, Klickitat County
Solar + storage
223 MWIn study Klickitat, WAWest Aug 2018target 2021
Solar project GI-TC-2024-28, Weld County
Solar
222 MWIn study Weld, COWest May 2023target 2027
Gas project Company 230, Clark County
Gas
222 MWAgreement signed Clark, NVWest Sep 2022target 2024
Page 16 of 38

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)