Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 159 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2813, Saginaw County
Solar
195 MWWithdrawn / abandoned Saginaw, MIMISO Sep 2022target 2027
Solar + storage project IA-PNM-2025-03, Mckinley County
Solar + storage
195 MWWithdrawn / abandoned Mckinley, NMWest Feb 2025target 2028
Solar project 25-IC-1362, Marengo County
Solar
195 MWWithdrawn / abandoned Marengo, ALSoutheast Apr 2025
Marcy BESS 2
Battery storage · The Commodore Storage, LLC
195 MWWithdrawn / abandoned Oneida, NYNYISO Sep 2024
Solar project J1551, Morehouse Parish County
Solar
195 MWWithdrawn / abandoned Morehouse Parish, LAMISO Jun 2020target 2024
Horizon Wind Energy-Wheat
Onshore wind · Wheat Field Power Partners, LLC
195 MWWithdrawn / abandoned Wasco, ORWest Sep 2001target 2005
Solar project 582, Lawrence County
Solar
195 MWWithdrawn / abandoned Lawrence, TNSoutheast Sep 2023target 2026
Solar + storage project GI-CS-2025-15, El Paso County
Solar + storage
195 MWWithdrawn / abandoned El Paso, COWest Sep 2025target 2028
Gas project J073, Blue Earth County
Gas
194 MWWithdrawn / abandoned Blue Earth, MNMISO Oct 2010target 2012
Onshore wind project J3206, Cerro Gordo County
Onshore wind
194 MWWithdrawn / abandoned Cerro Gordo, IAMISO Sep 2022target 2027
Onshore wind project GEN-2024-107, Okmulgee County
Onshore wind
194 MWWithdrawn / abandoned Okmulgee, OKSPP Mar 2025target 2031
Solar project J1668, Iberville Parish County
Solar
194 MWWithdrawn / abandoned Iberville Parish, LAMISO Jun 2020target 2023
M Bar Wind
Onshore wind · Penn Real Estate Group, LTD
194 MWWithdrawn / abandoned ERCOT Jan 2007
Gas project W3-174, Salem County
Gas
194 MWWithdrawn / abandoned Salem, NJPJM Oct 2010target 2015
Keyhole 3
Battery storage
193 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Gas project Y2-102, Salem County
Gas
193 MWWithdrawn / abandoned Salem, NJPJM Nov 2012target 2016
Clover Leaf Hollers Ave
Gas · Clover Leaf Power, LLC
193 MWWithdrawn / abandoned Bronx, NYNYISO Oct 2011
Solar project GEN-2017-116, Curry County
Solar
193 MWWithdrawn / abandoned Curry, NMSPP Nov 20172024
Solar project GEN-2022-079, Cedar County
Solar
192 MWWithdrawn / abandoned Cedar, MOSPP Sep 2022target 2027
Solar project AG1-235, City Of Chesapeake County
Solar
192 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Sep 2020target 2024
Saavi Imperial Energy Storage
Battery storage
192 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Hydro project 956469, Oconee County
Hydro
192 MWWithdrawn / abandoned Oconee, SCSoutheast Jun 2024
Onshore wind project 398-A, Bonneville County
Onshore wind
192 MWWithdrawn / abandoned Bonneville, IDWest Aug 2011target 2012
Gas project 311, Morgan County
Gas
192 MWWithdrawn / abandoned Morgan, TNSoutheast Mar 2017
Celestine Storage
Battery storage · Hanwha Q CELLS USA
191 MWWithdrawn / abandoned Steuben, NYNYISO Mar 2022
Pistachio Energy Park
Solar + storage
191 MWWithdrawn / abandoned Kern, CACAISO Apr 2015target 2020
Onshore wind project GEN-2023-011, Jefferson County
Onshore wind
190 MWWithdrawn / abandoned Jefferson, NESPP Oct 2023target 2030
Gas project G267, Mcleod County
Gas
190 MWWithdrawn / abandoned Mcleod, MNMISO Nov 2002target 2007
Solar + storage project 25-IC-1351, Barbour County
Solar + storage
190 MWWithdrawn / abandoned Barbour, ALSoutheast Apr 2025
Gemma Storage
Battery storage · Hanwha Q CELLS USA
190 MWWithdrawn / abandoned Steuben, NYNYISO Mar 2022
Solar project GEN-2023-041, Mcintosh County
Solar
190 MWWithdrawn / abandoned Mcintosh, OKSPP Oct 2023target 2030
Battery storage project C3-182, Salt Lake County
Battery storage
190 MWWithdrawn / abandoned Salt Lake, UTWest May 2023target 2029
Affordable Solar
Solar + storage
190 MWWithdrawn / abandoned Rio Arriba, NMWest Jul 2018target 2021
Four Rivers NUG CC
Gas
190 MWWithdrawn / abandoned Hanover, VAPJM Jan 2008target 2017
Battery storage project G0638, Klickitat County
Battery storage
190 MWWithdrawn / abandoned Klickitat, WAWest Jan 2020target 2022
Onshore wind project C1-53, Albany County
Onshore wind
190 MWWithdrawn / abandoned Albany, WYWest May 2021target 2024
Battery storage project PIS046, Salt Lake County
Battery storage
190 MWWithdrawn / abandoned Salt Lake, UTWest Dec 2023target 2027
Solar project J2018, Clark County
Solar
190 MWWithdrawn / abandoned Clark, WIMISO Nov 2021target 2026
Solar + storage project 201, Kershaw County
Solar + storage
190 MWWithdrawn / abandoned Kershaw, SCSoutheast Jun 2023target 2027
Solar + storage project 1210, Klamath County
Solar + storage
190 MWWithdrawn / abandoned Klamath, ORWest Apr 2020target 2023
Solar + storage project 112, Lincoln County
Solar + storage
190 MWWithdrawn / abandoned Lincoln, WAWest Jan 2021target 2024
Onshore wind project J897, Grand Forks County
Onshore wind
190 MWWithdrawn / abandoned Grand Forks, NDMISO Jun 2017target 2024
Solar project J3257, Pulaski County
Solar
190 MWWithdrawn / abandoned Pulaski, INMISO Apr 2024target 2026
Wellhead Power Otay Mesa
Gas
190 MWWithdrawn / abandoned San Diego, CACAISO Jul 2009target 2013
Onshore wind project GEN-2017-015, Johnson County
Onshore wind
190 MWWithdrawn / abandoned Johnson, OKSPP Apr 2017target 2019
Battery Storage
Battery storage
190 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2023target 2027
Battery storage project GEN-2024-172, Grady County
Battery storage
190 MWWithdrawn / abandoned Grady, OKSPP Mar 2025target 2028
Battery storage project J2766, Howard County
Battery storage
190 MWWithdrawn / abandoned Howard, INMISO Aug 2023target 2025
Solar + storage project J3536, Poinsett County
Solar + storage
190 MWWithdrawn / abandoned Poinsett, ARMISO Apr 2024target 2028
Onshore wind project J1961, Cass County
Onshore wind
190 MWWithdrawn / abandoned Cass, NDMISO Aug 2021target 2026
Page 159 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)