HYDRO Β· SOUTHEASTHydro project 956469, Oconee County
Hydro project 956469, Oconee County is a 192 MW hydro request withdrawn in the Southeast interconnection queue, in Oconee County, South Carolina, connecting to Duke Energy Carolinas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 956469
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Carolinas
- Connection point (POI)
- Bad Creek Hydro Substation 500 kV
- Location
- Oconee County, South Carolina
- Technology
- Hydro: 192 MW
- Total requested
- 192 MW
- Service type
- Network resource (NRIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 20 June 2024
Location
Marker shows the centre of Oconee County; the queue data does not give exact sites.
Power plants in South Carolina Β· Transmission lines in South Carolina
Other requests in Oconee County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem