Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,752246.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,752 requests ยท page 14 of 36
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AG1-134, King William County
Solar ยท Virginia Electric and Power Company
100 MWWithdrawn / abandoned King William, VAPJM Sep 2020target 2024
Solar project J1722, Lonoke County
Solar
100 MWWithdrawn / abandoned Lonoke, ARMISO Jun 2020target 2024
Battery storage project 20-084, Marion County
Battery storage
100 MWWithdrawn / abandoned Marion, ORWest May 2020target 2023
Solar project J1740, Walworth County
Solar
100 MWWithdrawn / abandoned Walworth, WIMISO Jun 2020target 2023
Battery storage project 82, Thurston County
Battery storage
100 MWWithdrawn / abandoned Thurston, WAWest May 2020target 2022
Solar project J1680, Cass County
Solar
100 MWWithdrawn / abandoned Cass, INMISO Jun 2020target 2023
Battery storage project Company 190, Clark County
Battery storage
100 MWWithdrawn / abandoned Clark, NVWest Feb 2020target 2023
Solar
Solar
100 MWWithdrawn / abandoned Penobscot, MEISO-NE Nov 2020target 2024
Solar project AG1-006, Jay County
Solar
100 MWWithdrawn / abandoned Jay, INPJM Apr 2020target 2023
Esker Solar Park II
Solar ยท Headwaters Wind Farm III LLC d/b/a Esker Solar Park LLC and Esker Solar Park II LLC
100 MWWithdrawn / abandoned Delaware, INPJM Sep 2020target 2024
Solar + storage project 140, Horry County
Solar + storage
100 MWWithdrawn / abandoned Horry, SCSoutheast May 2020target 2022
Battery storage project AF2-071, Mercer County
Battery storage
100 MWWithdrawn / abandoned Mercer, NJPJM Jan 2020target 2023
Solar project J1580, Ottawa County
Solar
100 MWWithdrawn / abandoned Ottawa, MIMISO Jun 2020target 2023
Solar project AG1-521, Lee County
Solar
100 MWWithdrawn / abandoned Lee, ILPJM Sep 2020target 2023
Soapstone Solar and BESS
Solar
100 MWWithdrawn / abandoned Clarke, VAPJM Sep 2020target 2023
Ripley Solar II
Solar
100 MWWithdrawn / abandoned Fairfield, OHPJM Sep 2020target 2027
Battery storage project AG1-151, Rockingham County
Battery storage ยท Prospect Power, LLC
100 MWWithdrawn / abandoned Rockingham, VAPJM Sep 2020target 2023
Solar project IC-881, Burke County
Solar
100 MWWithdrawn / abandoned Burke, GASoutheast Jun 2020
Solar
Solar
100 MWWithdrawn / abandoned Penobscot, MEISO-NE Sep 2020target 2024
Solar project J1510, Wood County
Solar
100 MWWithdrawn / abandoned Wood, WIMISO Jun 2020target 2023
Battery storage project 85, Skagit County
Battery storage
100 MWWithdrawn / abandoned Skagit, WAWest Jul 2020target 2023
Battery storage project 433, Clay County
Battery storage
100 MWWithdrawn / abandoned Clay, MSSoutheast May 2020target 2023
Solar project IC-923, Pearl River County
Solar
100 MWWithdrawn / abandoned Pearl River, MSSoutheast Dec 2020
Battery storage project GEN-2021-002, Blaine County
Battery storage
100 MWWithdrawn / abandoned Blaine, OKSPP Dec 2020target 2027
Solar project J1634, Beauregard Parish County
Solar
100 MWWithdrawn / abandoned Beauregard Parish, LAMISO Jun 2020target 2022
Solar project IC-877, Hale County
Solar
100 MWWithdrawn / abandoned Hale, ALSoutheast Jun 2020
Alfred Oaks Solar
Solar + storage ยท Northland Power U.S. Projects
100 MWWithdrawn / abandoned Allegany, NYNYISO Sep 2020
Solar project AF2-390, Cass County
Solar
100 MWWithdrawn / abandoned Cass, MIPJM Mar 2020target 2023
Solar project J1622, Sheridan County
Solar
100 MWWithdrawn / abandoned Sheridan, NDMISO Jun 2020target 2024
Solar project J1555, Hillsdale County
Solar
100 MWWithdrawn / abandoned Hillsdale, MIMISO Jun 2020target 2023
Solar project J1694, Lawrence County
Solar
100 MWWithdrawn / abandoned Lawrence, INMISO Jun 2020target 2024
Battery storage project AF2-412, Tioga County
Battery storage ยท Elk Run LLC
100 MWWithdrawn / abandoned Tioga, PAPJM Mar 2020target 2022
Solar project J1624, Bartholomew County
Solar
100 MWWithdrawn / abandoned Bartholomew, INMISO Jun 2020target 2024
Solar + storage project 1198, Yakima County
Solar + storage
100 MWWithdrawn / abandoned Yakima, WAWest Feb 2020target 2023
Solar + storage project IC-907, Peach County
Solar + storage
100 MWWithdrawn / abandoned Peach, GASoutheast Oct 2020
Battery storage project AG1-556, Rockbridge County
Battery storage ยท Sand Dragon Energy LLC
100 MWWithdrawn / abandoned Rockbridge, VAPJM Sep 2020target 2024
Solar project AG1-424, Allen County
Solar ยท Leeward Renewable Energy Development, LLC
100 MWWithdrawn / abandoned Allen, INPJM Sep 2020target 2023
Solar project J1608, Ingham County
Solar
100 MWWithdrawn / abandoned Ingham, MIMISO Jun 2020target 2023
Solar + storage project 444, Mcnairy County
Solar + storage
100 MWWithdrawn / abandoned Mcnairy, TNSoutheast Jun 2020
Battery storage project S0001, Klamath County
Battery storage
100 MWWithdrawn / abandoned Klamath, ORWest Jul 2020target 2024
Solar + storage project IC-896, Hale County
Solar + storage
100 MWWithdrawn / abandoned Hale, ALSoutheast Jul 2020
Battery storage project IC-934, Bartow County
Battery storage
100 MWWithdrawn / abandoned Bartow, GASoutheast Dec 2020
Solar project J1797, St. John The Baptist Parish County
Solar
100 MWWithdrawn / abandoned St. John The Baptist Parish, LAMISO Jun 2020target 2023
Solar project AG1-438, Bertie County
Solar ยท RWE Solar Development, LLC
100 MWWithdrawn / abandoned Bertie, NCPJM Sep 2020target 2023
Battery storage project AG1-137, Rockingham County
Battery storage
100 MWWithdrawn / abandoned Rockingham, VAPJM Sep 2020target 2023
Solar project AG1-328, Union County
Solar
100 MWWithdrawn / abandoned Union, OHPJM Sep 2020target 2023
Solar project AG2-007, King William County
Solar
100 MWWithdrawn / abandoned King William, VAPJM Oct 2020target 2023
Battery storage project IA-PNM-2020-15, Bernalillo County
Battery storage
100 MWWithdrawn / abandoned Bernalillo, NMWest Sep 2020target 2023
Blackford County Solar
Solar ยท Blackford County Wind Farm LLC d/b/a Blackford County Solar Park LLC
100 MWWithdrawn / abandoned Blackford, INPJM Sep 2020target 2024
Solar project IC-922, Newton County
Solar
100 MWWithdrawn / abandoned Newton, MSSoutheast Dec 2020target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)