πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Carolina

SOLAR Β· PJM

Solar project AG1-438, Bertie County

Solar project AG1-438, Bertie County is a 100 MW solar request withdrawn in the PJM interconnection queue, in Bertie County, North Carolina, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2020 (completed)
  2. Withdrawn / abandonedJan 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG1-438
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
RWE Solar Development, LLC
Connection point (POI)
Cashie-Earleys 230 kV
Location
Bertie County, North Carolina
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
30 September 2020
Proposed online date
December 2023
Withdrawn
January 2025

Location

Marker shows the centre of Bertie County; the queue data does not give exact sites.

Power plants in North Carolina Β· Transmission lines in North Carolina

Other requests in Bertie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem