Solar project AG2-382, Bertie County

Solar project AG2-382, Bertie County is a 70.0 MW solar request in interconnection study in the PJM interconnection queue, in Bertie County, North Carolina, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-382
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
Merry Hill PV I, LLC
Connection point (POI)
Cashie 230 kV
Location
Bertie County, North Carolina
Technology
Solar: 70.0 MW
Total requested
70.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
7 February 2025
Proposed online date
September 2024

Location

Marker shows the centre of Bertie County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Bertie County