SOLAR Β· PJM

Solar project AD1-132, Bertie County

Solar project AD1-132, Bertie County is a 150 MW solar request withdrawn in the PJM interconnection queue, in Bertie County, North Carolina, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2017 (completed)
  2. Withdrawn / abandonedOct 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AD1-132
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Cashie 230 kV
Location
Bertie County, North Carolina
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
29 September 2017
Proposed online date
December 2019
Withdrawn
October 2017

Location

Marker shows the centre of Bertie County; the queue data does not give exact sites.

Power plants in North Carolina Β· Transmission lines in North Carolina

Other requests in Bertie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem