United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 132

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 132 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project T183, White County
Onshore wind
200 MWWithdrawn / abandoned White, INPJM Jan 2008target 2010
Solar project J3044, Tazewell County
Solar
200 MWWithdrawn / abandoned Tazewell, ILMISO Sep 2022target 2026
Onshore wind project J2784, Sangamon County
Onshore wind
200 MWWithdrawn / abandoned Sangamon, ILMISO Sep 2022target 2026
Onshore wind project GEN-2024-094, Meade County
Onshore wind
200 MWWithdrawn / abandoned Meade, KSSPP Mar 2025target 2028
Onshore wind project GEN-2014-052, Beaver County
Onshore wind
200 MWWithdrawn / abandoned Beaver, OKSPP Sep 2014target 2016
Solar project Q10, Pinal County
Solar
200 MWWithdrawn / abandoned Pinal, AZWest Sep 2018target 2022
Onshore wind project J1366, Eau Claire County
Onshore wind
200 MWWithdrawn / abandoned Eau Claire, WIMISO Apr 2019target 2022
Battery storage project 1180, Juab County
Battery storage
200 MWWithdrawn / abandoned Juab, UTWest Oct 2019target 2023
Solar project G0545, Klamath County
Solar
200 MWWithdrawn / abandoned Klamath, ORWest Jun 2016target 2019
Solar project J1540, Cass County
Solar
200 MWWithdrawn / abandoned Cass, NDMISO Jun 2020target 2024
Sweet Valley Storage
Battery storage · Sweet Valley Energy Center, LLC
200 MWWithdrawn / abandoned Genesee, NYNYISO Sep 2024
Onshore wind project G988, Mcintosh County
Onshore wind
200 MWWithdrawn / abandoned Mcintosh, NDMISO Mar 2008target 2009
Solar project IC-871, Clarke County
Solar
200 MWWithdrawn / abandoned Clarke, MSSoutheast May 2020
Goldwick Solar Farm
Solar + storage
200 MWWithdrawn / abandoned Stanislaus, CACAISO May 2017target 2020
Solar project J1217, St. Landry Parish County
Solar
200 MWWithdrawn / abandoned St. Landry Parish, LAMISO Apr 2019target 2022
Solar project J3350, Randolph County
Solar
200 MWWithdrawn / abandoned Randolph, MOMISO Apr 2024target 2028
Battery storage project GEN-2022-240, Hempstead County
Battery storage
200 MWWithdrawn / abandoned Hempstead, ARSPP Feb 2023target 2028
Coal project X1-027, Scioto County
Coal
200 MWWithdrawn / abandoned Scioto, OHPJM Mar 2011target 2014
Battery storage project J2105, Franklin County
Battery storage
200 MWWithdrawn / abandoned Franklin, IAMISO Aug 2021target 2024
Onshore wind project GEN-2015-086, Woodward County
Onshore wind
200 MWWithdrawn / abandoned Woodward, OKSPP Sep 2015target 2018
Onshore wind project GEN-2006-038N010, Cedar County
Onshore wind
200 MWWithdrawn / abandoned Cedar, NESPP Oct 2006
Trans Pecos II Wind Farm
Onshore wind · Horizon Wind Energy
200 MWWithdrawn / abandoned ERCOT Feb 2008target 2050
Battery storage project 24-256, Washington County
Battery storage
200 MWWithdrawn / abandoned Washington, ORWest May 2024target 2027
Onshore wind project GI-0902, Codington County
Onshore wind
200 MWWithdrawn / abandoned Codington, SDWest Jan 2009target 2012
Gas project TCS-13, Kootenai County
Gas
200 MWWithdrawn / abandoned Kootenai, IDWest Nov 2020target 2026
Onshore wind project J1114, Plymouth County
Onshore wind
200 MWWithdrawn / abandoned Plymouth, IAMISO Mar 2018target 2021
Solar + storage project Company MD, Lyon County
Solar + storage
200 MWWithdrawn / abandoned Lyon, NVWest Sep 2021target 2026
Solar + storage project Q421, Navajo County
Solar + storage
200 MWWithdrawn / abandoned Navajo, AZWest Sep 2021target 2025
200MW North Lewiston-Walla Walla 1
Onshore wind · RES North America
200 MWWithdrawn / abandoned Walla Walla, WAWest Sep 2001target 2002
Onshore wind project G0356, Wheatland County
Onshore wind
200 MWWithdrawn / abandoned Wheatland, MTWest Mar 2009target 2015
Solar + storage project J2201, Harrison County
Solar + storage
200 MWWithdrawn / abandoned Harrison, INMISO Dec 2021target 2024
Solar project IC-704, Lee County
Solar
200 MWWithdrawn / abandoned Lee, GASoutheast May 2018
Onshore wind project GEN-2017-098, Meade County
Onshore wind
200 MWWithdrawn / abandoned Meade, SDSPP May 2017target 2020
Wishbone Solar
Solar · ACE DevCo NC, LLC
200 MWWithdrawn / abandoned Steuben, NYNYISO Dec 2022
Solar project 988, Converse County
Solar
200 MWWithdrawn / abandoned Converse, WYWest Dec 2017target 2020
Solar project J2295, Sullivan County
Solar
200 MWWithdrawn / abandoned Sullivan, INMISO Sep 2021target 2025
Alwest
Gas
200 MWWithdrawn / abandoned Anderson, TXERCOT Jul 2018
Battery storage project 452, Lewis And Clark County
Battery storage
200 MWWithdrawn / abandoned Lewis And Clark, MTWest Oct 2023target 2030
Solar + storage project G1011, Lake County
Solar + storage
200 MWWithdrawn / abandoned Lake, ORWest Nov 2023target 2027
Solar project J3261, Tunica County
Solar
200 MWWithdrawn / abandoned Tunica, MSMISO Mar 2024target 2028
Solar project J2113, Daviess County
Solar
200 MWWithdrawn / abandoned Daviess, KYMISO Aug 2021target 2024
Onshore wind project J1065, Gratiot County
Onshore wind
200 MWWithdrawn / abandoned Gratiot, MIMISO Mar 2018target 2020
Battery storage project 621, Bay County
Battery storage · FPL
200 MWWithdrawn / abandoned Bay, FLSoutheast Jan 2024target 2027
Onshore wind project 23-224, Columbia County
Onshore wind
200 MWWithdrawn / abandoned Columbia, ORWest Mar 2023target 2028
March Road Solar
Solar · Eon
200 MWWithdrawn / abandoned Tom Green, TXERCOT Nov 2017target 2021
Onshore wind project GEN-2003-002, Greenwood County
Onshore wind
200 MWWithdrawn / abandoned Greenwood, KSSPP Mar 2003target 2004
Solar + storage project 63, Pima County
Solar + storage
200 MWWithdrawn / abandoned Pima, AZWest Sep 2018target 2021
Faraday Energy Storage
Battery storage
200 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Battery storage project IC-1175, Etowah County
Battery storage
200 MWWithdrawn / abandoned Etowah, ALSoutheast Sep 2023target 2027
Battery storage project 22-04121, Larimer County
Battery storage
200 MWWithdrawn / abandoned Larimer, COWest Apr 2022target 2026
Page 132 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)