Battery storage project GEN-2022-240, Hempstead County

Battery storage project GEN-2022-240, Hempstead County is a 200 MW battery storage request withdrawn in the SPP interconnection queue, in Hempstead County, Arkansas, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-240
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
John W Turk Jr Power Plant 345 kV sub
Location
Hempstead County, Arkansas
Technology
Battery: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
28 February 2023
Proposed online date
September 2028
Withdrawn
March 2025

Location

Marker shows the centre of Hempstead County; the queue data does not give exact sites.