🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Arkansas

COAL · SPP

Coal project GEN-2013-011, Hempstead County

Coal project GEN-2013-011, Hempstead County is a 30.0 MW coal request built and operating in the SPP interconnection queue, in Hempstead County, Arkansas, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Mar 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2013-011
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Turk 138kV
Location
Hempstead County, Arkansas
Technology
Coal: 30.0 MW
Total requested
30.0 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
28 March 2013
Proposed online date
December 2012
Came online
December 2012

Location

Marker shows the centre of Hempstead County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Other requests in Hempstead County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem