United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2019 requests) โ€” page 13

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,473226.5 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,473 requests ยท page 13 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project IC-820, Douglas County
Battery storage
100 MWWithdrawn / abandoned Douglas, GASoutheast Oct 2019target 2022
Solar project 125, Berkeley County
Solar
100 MWWithdrawn / abandoned Berkeley, SCSoutheast Mar 2019target 2020
Solar project BHCT G27, Pueblo County
Solar
100 MWWithdrawn / abandoned Pueblo, COWest Dec 2019target 2022
Myrtle Solar II
Solar ยท Myrtle Solar II, LLC
100 MWWithdrawn / abandoned Brazoria, TXERCOT Mar 2019target 2022
Kce NY 12
Battery storage ยท KCE NY 12, LLC
100 MWWithdrawn / abandoned Suffolk, NYNYISO Nov 2019
Solar project AF1-076, Allen County
Solar
100 MWWithdrawn / abandoned Allen, OHPJM Aug 2019target 2021
White Spring ES
Battery storage ยท sPower Development Company, LLC
100 MWWithdrawn / abandoned Ontario, NYNYISO Oct 2019
Solar project J1279, Hardin County
Solar
100 MWWithdrawn / abandoned Hardin, TXMISO Apr 2019target 2022
Hayden Run
Solar
100 MWWithdrawn / abandoned Franklin, OHPJM Sep 2019target 2023
New Bremen Solar
Solar ยท New Bremen Solar, LLC
100 MWWithdrawn / abandoned Lewis, NYNYISO Jun 2019
Solar project GEN-2019-069, Madison County
Solar
100 MWWithdrawn / abandoned Madison, NESPP May 2019target 2027
Solar project AF1-276, Mckean County
Solar ยท McKean Solar, LLC
100 MWWithdrawn / abandoned Mckean, PAPJM Sep 2019target 2024
Solar project J1443, Union County
Solar
100 MWWithdrawn / abandoned Union, ARMISO Apr 2019target 2023
Clermont 1
Battery storage ยท Hecate Grid Clermont 1 LLC
100 MWWithdrawn / abandoned Suffolk, NYNYISO Oct 2019
Solar project AE2-157, Sussex County
Solar
100 MWWithdrawn / abandoned Sussex, VAPJM Mar 2019target 2021
Solar project G0629, Benton County
Solar
100 MWWithdrawn / abandoned Benton, WAWest Sep 2019target 2024
Battery storage project J1468, Dakota County
Battery storage
100 MWWithdrawn / abandoned Dakota, MNMISO Apr 2019target 2022
Battery storage project IC-822, Clayton County
Battery storage
100 MWWithdrawn / abandoned Clayton, GASoutheast Oct 2019
Solar project LGE-GIS-2019-029, Hardin County
Solar
100 MWWithdrawn / abandoned Hardin, KYSoutheast Nov 2019target 2024
Battery storage project J1479, Des Moines County
Battery storage
100 MWWithdrawn / abandoned Des Moines, IAMISO Apr 2019target 2023
Catskill Grid, LLC
Battery storage ยท Catskill Grid, LLC
100 MWWithdrawn / abandoned Greene, NYNYISO Dec 2019
Solar project LGE-GIS-2019-010, Lyon County
Solar
100 MWWithdrawn / abandoned Lyon, KYSoutheast Mar 2019target 2021
Battery storage project IC-829, Fulton County
Battery storage
100 MWWithdrawn / abandoned Fulton, GASoutheast Oct 2019
Solar project GEN-2019-073, Madison County
Solar
100 MWWithdrawn / abandoned Madison, NESPP May 2019target 2027
Cayuga Grid, LLC
Battery storage ยท Cayuga Grid, LLC
100 MWWithdrawn / abandoned Erie, NYNYISO Dec 2019
Solar project J1385, Hendricks County
Solar
100 MWWithdrawn / abandoned Hendricks, INMISO Apr 2019target 2022
Battery storage project Q59, Maricopa County
Battery storage
100 MWWithdrawn / abandoned Maricopa, AZWest Jun 2019target 2023
Solar project AE2-328, Accomack County
Solar
100 MWWithdrawn / abandoned Accomack, VAPJM Mar 2019target 2022
Solar project J1278, Polk County
Solar
100 MWWithdrawn / abandoned Polk, TXMISO Apr 2019target 2022
Solar project LGE-GIS-2019-004, Breckinridge County
Solar
100 MWWithdrawn / abandoned Breckinridge, KYSoutheast Feb 2019target 2026
Onshore wind project J1376, Cooper County
Onshore wind
100 MWWithdrawn / abandoned Cooper, MOMISO Apr 2019target 2022
Solar project J1253, Fond Du Lac County
Solar
100 MWWithdrawn / abandoned Fond Du Lac, WIMISO Apr 2019target 2024
Solar + storage project Company 186, Clark County
Solar + storage
100 MWWithdrawn / abandoned Clark, NVWest Sep 2019target 2022
Solar + storage project AF1-304, Venango County
Solar + storage
100 MWWithdrawn / abandoned Venango, PAPJM Sep 2019target 2023
Battery storage project GEN-2019-077, Lancaster County
Battery storage
100 MWWithdrawn / abandoned Lancaster, NESPP May 2019target 2022
Loomis Creek Solar
Solar ยท sPower Development Company, LLC
100 MWWithdrawn / abandoned Columbia, NYNYISO Oct 2019
Solar project LGE-GIS-2019-019, Union County
Solar
100 MWWithdrawn / abandoned Union, KYSoutheast Mar 2019target 2021
Solar project LGE-GIS-2019-014, Ballard County
Solar
100 MWWithdrawn / abandoned Ballard, KYSoutheast Mar 2019target 2021
Solar project LGE-GIS-2019-012, Muhlenberg County
Solar
100 MWWithdrawn / abandoned Muhlenberg, KYSoutheast Mar 2019target 2021
Battery storage project Q298, Maricopa County
Battery storage
100 MWWithdrawn / abandoned Maricopa, AZWest Mar 2019target 2023
Solar project 2019-G6
Solar
100 MWWithdrawn / abandoned West May 2019target 2021
Solar project J1423, Ottawa County
Solar
100 MWWithdrawn / abandoned Ottawa, MIMISO Apr 2019target 2022
Solar project 19-04261, Larimer County
Solar
100 MWWithdrawn / abandoned Larimer, COWest Apr 2019target 2021
Port Jefferson Power Station Battery Energy Storage System (BESS)
Battery storage ยท National Grid Generation LLC
100 MWWithdrawn / abandoned Suffolk, NYNYISO Nov 2019
Solar project LGE-GIS-2019-018, Mclean County
Solar
100 MWWithdrawn / abandoned Mclean, KYSoutheast Mar 2019target 2021
Battery storage project GEN-2019-074, Lamb County
Battery storage
100 MWWithdrawn / abandoned Lamb, TXSPP May 20192023
Gas project AF1-065, Brooke County
Gas
100 MWWithdrawn / abandoned Brooke, WVPJM Jul 2019target 2022
Yonkers Grid, LLC
Battery storage ยท Yonkers Grid, LLC
100 MWWithdrawn / abandoned Westchester, NYNYISO Mar 2019
Solar + storage project Company JS, Pershing County
Solar + storage
100 MWWithdrawn / abandoned Pershing, NVWest Mar 2019target 2021
Onshore wind project 1131, Carbon County
Onshore wind
100 MWWithdrawn / abandoned Carbon, WYWest Apr 2019target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)