SOLAR Β· MISO

Solar project J1278, Polk County

Solar project J1278, Polk County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Polk County, Texas, connecting to ENTERGY TEXAS, INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedAug 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1278
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY TEXAS, INC.
Connection point (POI)
Corrigan Bulk - Staley 138kV Line
Location
Polk County, Texas
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
29 April 2019
Proposed online date
March 2022
Withdrawn
August 2020

Location

Marker shows the centre of Polk County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Polk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem