Myrtle Solar II

Myrtle Solar II is a 100 MW solar request withdrawn in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2019 (completed)
  2. Withdrawn / abandonedSep 2021 (project stopped here)
  3. ConsentedFeb 2021 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0263
Grid region
ERCOT (Texas)
Developer
Myrtle Solar II, LLC
Connection point (POI)
42110 Angleton 138kV
Location
Brazoria County, Texas
Technology
Solar: 100 MW
Total requested
100 MW
Study phase
IA
Queue status
Withdrawn
Entered queue
24 March 2019
Agreement signed
1 February 2021
Proposed online date
December 2022
Withdrawn
September 2021

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem