United States βΊ Grid βΊ Interconnection queues βΊ Iowa
BATTERY STORAGE Β· MISOBattery storage project J1479, Des Moines County
Battery storage project J1479, Des Moines County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Des Moines County, Iowa, connecting to ITC MIDWEST.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedFeb 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1479
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Burlington 161 kV Substation
- Location
- Des Moines County, Iowa
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 29 April 2019
- Proposed online date
- October 2023
- Withdrawn
- February 2022
Location
Marker shows the centre of Des Moines County; the queue data does not give exact sites.
Other requests in Des Moines County
- Solar project J1135, Des Moines CountySolar Β· 50.0 MW Β· agreement signed
- Replacing 30 MW of existing coal generation with BESS at Burlington Generation Station; Burlington 5Other Β· 212 MW Β· in study
- Other project G127, Des Moines CountyOther Β· 600 MW Β· withdrawn
- Other project G126, Des Moines CountyOther Β· 325 MW Β· withdrawn
- Onshore wind project J097, Des Moines CountyOnshore wind Β· 200 MW Β· withdrawn
- Solar project J1972, Des Moines CountySolar Β· 115 MW Β· withdrawn
- Battery storage project J1853, Des Moines CountyBattery storage Β· 50.0 MW Β· withdrawn
- Replacing 31 MW of generation with linear generators powered by natural gas; Burlington 3Gas Β· 31.0 MW Β· withdrawn
- Battery storage project J1478, Des Moines CountyBattery storage Β· 25.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem