White Spring ES

White Spring ES is a 100 MW battery storage request withdrawn in the NYISO interconnection queue, in Ontario County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2019 (completed)
  2. Withdrawn / abandonedJun 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
919
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
sPower Development Company, LLC
Connection point (POI)
Haley Road Substation 115 kV
Location
Ontario County, New York
Technology
Battery: 100 MW
Total requested
100 MW
Queue status
Withdrawn
Entered queue
10 October 2019
Withdrawn
June 2021

Location

Marker shows the centre of Ontario County; the queue data does not give exact sites.