United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA — page 126

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 126 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AI2-013, Grundy County
Solar
24.1 MWIn study Grundy, ILPJM Nov 2022target 2026
Nuclear project 637, Hamilton County
Nuclear
24.0 MWIn study Hamilton, TNSoutheast Aug 2024target 2027
Solar project AI2-154, Centre County
Solar
24.0 MWIn study Centre, PAPJM Mar 2023target 2025
Hydro project 655, Hamilton County
Hydro
24.0 MWIn study Hamilton, TNSoutheast Sep 2024target 2028
Hydro project 654, Hamilton County
Hydro
24.0 MWIn study Hamilton, TNSoutheast Sep 2024target 2028
Solar project AI2-135, Mclean County
Solar
24.0 MWIn study Mclean, ILPJM Feb 2023target 2025
Gas project AH1-719, Washington County
Gas · Washington Power Generation LLC
24.0 MWIn study Washington, OHPJM Apr 2025
Gas project AH1-686, Lawrence County
Gas · Hanging Rock Power Company LLC
24.0 MWIn study Lawrence, OHPJM Apr 2025
Solar project AI2-169, Cass County
Solar
24.0 MWIn study Cass, MIPJM Mar 2023target 2025
Solar project AI2-418, Allen County
Solar
24.0 MWIn study Allen, INPJM Mar 2023target 2026
Gas project AH1-704, Monroe County
Gas · Long Ridge Energy Generation LLC
24.0 MWIn study Monroe, OHPJM Apr 2025
Solar + storage project T2-088, Lake County
Solar + storage
23.5 MWIn study Lake, ORWest Sep 2025target 2027
Solar project J1927, Muscatine County
Solar
23.4 MWIn study Muscatine, IAMISO Dec 2021target 2027
CPS Energy AvR1CT2 Rotor Replacement
Gas · CPS Energy
23.2 MWIn study Bexar, TXERCOT Oct 2023target 2025
Solar project AI2-340, Van Buren County
Solar
23.1 MWIn study Van Buren, MIPJM Mar 2023target 2025
Gas project 20211104002, Calhoun County
Gas · DESC - Generation
23.0 MWIn study Calhoun, SCSoutheast target 2022
Solar project AI2-341, Marion County
Solar
22.8 MWIn study Marion, OHPJM Mar 2023target 2024
Brazos Wind Repower
Onshore wind · BRAZOS WIND VENTURES, LLC
22.4 MWIn study Scurry, TXERCOT Dec 2020target 2025
Solar project LGE-GIS-2024-004, Mercer County
Solar
22.0 MWIn study Mercer, KYSoutheast Apr 2024target 2026
Other project 977788, Columbus County
Other
22.0 MWIn study Columbus, NCSoutheast Jun 2025
Solar project J3993, Wayne County
Solar
21.4 MWIn study Wayne, ILMISO Apr 2025target 2027
Nuclear project J4010, Dewitt County
Nuclear
21.0 MWIn study Dewitt, ILMISO Apr 2025target 2027
Brandon
Gas
21.0 MWPaused / redesign Lubbock, TXERCOT Sep 2018target 2021
Surplus; G291
Other
21.0 MWIn study MISO Sep 2024target 2026
Solar project AH1-059, Knox County
Solar · Frasier Solar, LLC
21.0 MWIn study Knox, OHPJM Mar 2025target 2024
Solar project AI2-374, Bath County
Solar
20.6 MWIn study Bath, KYPJM Mar 2023target 2025
Solar project AI2-415, Butler County
Solar
20.3 MWIn study Butler, PAPJM Mar 2023target 2026
Replacing 20 MW of solar with storage; J1746
Other
20.2 MWIn study Columbia, WIMISO Apr 2025target 2026
Somers Solar, LLC
Solar · Somers Solar, LLC
20.0 MWIn study Washington, NYNYISO May 2020target 2026
Solar + storage project T2-042, Millard County
Solar + storage
20.0 MWIn study Millard, UTWest Sep 2025target 2027
Concho Solar I
Solar
20.0 MWPaused / redesign Queen Anne's, MDPJM May 2019target 2024
Coal project GI-40, New Madrid County
Coal
20.0 MWIn study New Madrid, MOSoutheast Oct 2009target 2011
Battery storage project G0734, Benton County
Battery storage
20.0 MWIn study Benton, WAWest Mar 2022target 2024
Momentum Gratz
Battery storage
20.0 MWPaused / redesign Dauphin, PAPJM Jun 2019target 2024
SunEast Skyline Solar LLC
Solar · SunEast Skyline Solar LLC
20.0 MWIn study Oneida, NYNYISO Sep 2017target 2028
Cedar Creek Solar
Solar
20.0 MWPaused / redesign Kent, DEPJM Apr 2017target 2027
SunEast Flat Stone Solar LLC
Solar · SED NY Holdings LLC
20.0 MWIn study Oneida, NYNYISO Mar 2020target 2026
Solar + storage project T2-006, Tooele County
Solar + storage · PacifiCorp
20.0 MWIn study Tooele, UTWest Aug 2025target 2028
Little Pond Solar
Solar · Little Pond Solar, LLC
20.0 MWIn study Orange, NYNYISO Sep 2016target 2027
Battery storage project AG2-380, Queen Anne's County
Battery storage · Concho Solar I, LLC
20.0 MWIn study Queen Anne's, MDPJM Dec 2024target 2023
Solar + storage project T2-009, Umatilla County
Solar + storage
20.0 MWIn study Umatilla, ORWest Aug 2025target 2027
Geothermal project Company RA, Pershing County
Geothermal
20.0 MWIn study Pershing, NVWest Oct 2024target 2029
Hills Solar
Solar · SunEast Hills Solar LLC
20.0 MWIn study Herkimer, NYNYISO Oct 2016target 2026
Battery storage project AH2-049, Somerset County
Battery storage
20.0 MWIn study Somerset, MDPJM Dec 2021target 2025
Mountain Holly
Solar
20.0 MWPaused / redesign Columbia, PAPJM Mar 2019target 2027
Solar + storage project AI1-153, Dauphin County
Solar + storage
20.0 MWIn study Dauphin, PAPJM Sep 2022target 2027
Hatchery Solar
Solar · Hatchery Solar LLC
20.0 MWIn study Livingston, NYNYISO Oct 2019target 2026
Battery storage project AH2-048, Northampton County
Battery storage
20.0 MWIn study Northampton, VAPJM Dec 2021target 2025
Solar + storage project 340, Yellowstone County
Solar + storage
20.0 MWIn study Yellowstone, MTWest Mar 2018target 2021
Solar project AH1-571
Solar · South Fork Solar, LLC
20.0 MWIn study KYPJM Mar 2025target 2024
Page 126 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)